Tue 9 Aug 2011 09:46

LNG bunkering factored into berth project


Singapore construction project to allow for potential future LNG bunkering opportunities.



Singapore LNG Corporation Pte. Ltd. (SLNG) has awarded the engineering, procurement, and construction (EPC) contract for the secondary berth of its LNG Terminal on Jurong Island.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3) which is being constructed by Samsung C&T Corporation (Samsung) as part of the current LNG Terminal EPC contract.

Secondary Berth Project Adds Potential to Develop Other Services of the LNG Terminal

"Overall the Secondary Berth Project adds flexibility and value to the range of LNG Terminal services that SLNG can offer its customers in Singapore and regionally. This is totally consistent with our goal of becoming a gas hub for the region," explained Mr Neil McGregor, SLNG’s Chief Executive Officer.

“We have a masterplan with built-in options to the LNG Terminal that will facilitate the majority of LNG market scenarios that are likely to develop in the region,” added McGregor.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

“With its additional berthing capacity, the Secondary Jetty will improve the resilience of the LNG Terminal and enable Singapore to import more LNG when required. This will add to EMA’s efforts to enhance Singapore’s energy security and diversify our natural gas supplies.” said Chee Hong Tat, Chief Executive, Energy Market Authority.

Award of the EPC Contract for Secondary Berth Project

The tender was keenly contested by four tenderers and some novel design alternatives were received as part of the tender process. After a rigorous and robust selection process, SLNG awarded the EPC contract to Samsung for an undisclosed sum. Apart from putting forward the most competitive and lowest priced tender, Samsung's design and engineering proposal was found to provide the best quality and to deliver the best value to SLNG. McGregor commented: "There are some synergistic benefits to having Samsung as a single contractor across both sites. However, the award was made on merit, considering each tender as a standalone proposal."

“Samsung is very pleased to be awarded the Secondary Berth Project by SLNG. Our success in this tender demonstrates Samsung’s continued commitment to making Singapore’s LNG Terminal a reality. We are confident of delivering both the LNG Terminal and Secondary Berth projects safely and within schedule,” said Paul Shin, Vice President & Head of South East Asia of Samsung C&T Corporation.

Main LNG Terminal on Track

The EPC work on the Secondary Berth will take approximately 29 months and is expected to begin in late August 2011 and targeted for completion in December 2013. The main LNG Terminal project is progressing well and is fast approaching 50 percent overall completion. Over two million man hours have been worked on site to date without lost time injury. Final commissioning of the LNG Terminal is expected to be completed on schedule for commercial operations to commence by second quarter of 2013.


Marius Kairys, CEO of Elenger Sp. z o.o. Elenger enters Polish LNG bunkering market with ferry refuelling operation  

Baltic energy firm completes maiden truck-to-ship LNG delivery in Gdansk.

Samsung Heavy Industries (SHI) virtual reality (VR) training program developed in collaboration with Evergreen. SHI develops VR training solutions for Evergreen's methanol-fuelled ships  

Shipbuilder creates virtual reality program for 16,500 TEU boxship operations.

Illustratic image of Itochu's newbuild ammonia bunkering vessel, scheduled for delivery in September 2027. Itochu orders 5,000 cbm ammonia bunker vessel  

Japanese firm targets Singapore demonstration after October 2027, with Zeta Bunkering lined up to perform deliveries.

Bunkering of the Glovis Selene car carrier. Shell completes first LNG bunkering operation with Hyundai Glovis in Singapore  

Energy major supplies fuel to South Korean logistics firm's dual-fuel vessel.

Orient Overseas Container Line (OOCL) vessel. CPN delivers first B30 marine gasoil to OOCL in Hong Kong  

Chimbusco Pan Nation claims to be first in region to supply all grades of ISCC-EU certified marine biofuel.

The Buffalo 404 barge, owned by Buffalo Marine Service Inc., performing a bunker delivery. TFG Marine installs first ISO-certified mass flow meter on US Gulf bunker barge  

Installation marks expansion of company's digitalisation programme across global fleet.

Sogestran's fuel supply vessel, the Anatife, at the port of Belle-Île-en-Mer. Sogestran's HVO-powered tanker achieves 78% CO2 reduction on French island fuel runs  

Small tanker Anatife saves fuel while supplying Belle-Île and Île d'Yeu.

Crowley 1,400 TEU LNG-powered containership, Tiscapa. Crowley deploys LNG-powered boxship Tiscapa for Caribbean and Central American routes  

Vessel is the third in company's Avance Class fleet to enter service.

The inland LNG bunker vessel LNG London. LNG London completes 1,000 bunkering operations in Rotterdam and Antwerp  

Delivery vessel reaches milestone after five years of operations across ARA hub.

The M.V. COSCO Shipping Yangpu, China's first methanol dual-fuel containership. COSCO vessel completes maiden green methanol bunkering at Yangpu  

China's first methanol dual-fuel containership refuels with green methanol derived from urban waste.


↑  Back to Top