This is a legacy page. Please click here to view the latest version.
Tue 28 Mar 2017, 13:46 GMT

Quadrise confirms two-shift production at Cepsa refinery


Manufacturing unit at San Roque switched to 24-hour production in January.



Quadrise Fuels International plc has confirmed that production of its MSAR fuel at Cepsa's San Roque refinery in Spain moved to a two-shift production schedule in January - operating the MSAR Manufacturing Unit (MMU) on a 24-hour basis to produce the largest single batch of MSAR to date.

In its interim results for the last six months of the year, the UK firm said that production of MSAR during the period had "progressed well" and that incremental enhancements to the MMU were "proving to be helpful as we build up our operational experience within a refinery that processes a variety of different crude oils".

Quadrise noted that, since the start of the year, it has also been working with Cepsa to examine new opportunities to maximize the MSAR production capacity at the San Roque facility. Discussions are said to be "progressing well".

Maersk trial could resume in Q4 2017

Maersk is also said to be reviewing options to recommence and complete a 'letter of no objection (LONO) trial' on a new vessel from the fourth quarter of 2017 onwards. It follows Maersk's recent cancellation of the trial, which was confirmed by Quadrise earlier this month.

Last year, in July, following the installation of an MSAR manufacturing unit at the San Roque site, trials commenced with MSAR fuel from the refinery being supplied to and burnt by a nominated Maersk vessel on its regular scheduled route.

Maersk is cited by Quadrise as saying that the trial "progressed well"; however, operational issues with the trial vessel, said to be totally unrelated to MSAR, resulted in Quadrise making two announcements, on 2nd and 13th March respectively. The first of these announcements confirmed that there had been an incident that would require the trial vessel to undergo an unscheduled dry dock visit. The second announcement, on 13th March, stated that Quadrise had been advised by Maersk that it would not be possible for the trial to continue on the vessel following the dry dock visit as it would then be redeployed on a different service that would not permit further bunkering at Algeciras.

As a result, it was confirmed that the current trial on this vessel would be suspended once the remaining MSAR fuel on board had been consumed.

Quadrise also said on 13th March that Wartsila will be carrying out a detailed interim inspection of the trial vessel's engine to document the performance of MSAR fuel to date.

Wartsila LONO: the commercial trigger point

Whilst Quadrise still aims to start commercial operations in 2017, and to begin the commercial delivery of MSAR from the Cepsa refinery to an expanding number of Maersk ships, the company concedes that the suspension of Maersk's trial will have an impact on this timetable.

Quadrise says that for Maersk, a positive interim inspection and LONO by Wartsila is the trigger point for commencing commercial discussions.

"Maersk's decision will ultimately be taken on several factors, primarily economic and operational, that will include the economic and environmental advantages of MSAR in addition to their chosen approach to compliance with the new IMO open ocean sulphur standards that come into force in 2020," Quadrise noted.

In addition to its continuing discussions with Maersk, Quadrise says that it has also been increasing its activities with other shipping operators and that an interim LONO from Wartsila "will be a very positive attribute in progressing those activities".

"Alongside this, we will be continuing our discussions with a number of other producers in the major European and Asian bunker hubs and regional refining centres to provide additional sourcing opportunities," Quadrise added.

Financial results

In its financial results for the last six months of 2016, Quadrise posted a loss of GBP 2.4 million. The production and development costs for the period amounted to GBP 1.3 million, most of which related to the ongoing LONO trial with Maersk.

As at 31st December, Quadrise held cash and cash equivalents of GBP 7.0 million. This includes GBP 5.0 million (net of costs) raised through a placing and open offer during the period.


Ubuntu Humanity alongside Fuelng Bellina vessel. DNV says existing LNG infrastructure can support low-GHG methane transition  

Classification society finds biomethane and e-methane compatible with current LNG fleet and bunkering networks.

IBIA bunker buyers working group graphic. IBIA launches Bunker Buyers Working Group for fuel procurement end users  

New forum aims to represent shipowners, charterers and ship managers in policy and regulatory discussions.

Carbon registry process diagram. MOL and Shell launch book-and-claim scheme for marine biofuel emissions credits  

Japanese shipping firm partners with Shell to offer environmental attribute certificates from third-party vessel operations.

Renewable Energy Directive (RED III) policy brief cover. Bureau Veritas releases report on EU Renewable Energy Directive’s impact on shipping  

Classification society examines RED III compliance challenges as member states transpose the directive into national law.

New York City skyline. IBIA to hold 2026 annual convention in New York  

The event marks the first time in recent years that the association’s gathering has been held in the Americas.

Port of Barcelona delegates. Port of Barcelona advances shore power rollout for cruise terminals  

Installation of OPS systems begins at MSC and Royal Caribbean terminals as port reorganises infrastructure.

NACKS bulk carriers with rotor sails. Anemoi and NACKS secure ClassNK approval for Ultramax rotor sail designs  

Two configurations for wind-assisted propulsion systems on bulk carriers receive approval in principle.

DP World London vessel. Elbdeich Reederei takes delivery of first methanol-capable feeder vessel  

German shipowner receives 1,250-teu dual-fuel newbuild from Chinese yard, with three more to follow.

AuctionConnect and Asyad Shipping logos. Asyad Shipping adopts AuctionConnect digital bunker platform under three-year deal  

Middle East shipping company to implement auction-based procurement system across fleet operations.

Fuel for thought: LNG for Cruise report cover. LNG remains the most deployable decarbonisation option for cruise shipping, Lloyd’s Register report finds  

Classification society’s latest research examines the fuel’s role in the sector’s energy transition and pathway to net zero.


↑  Back to Top