This is a legacy page. Please click here to view the latest version.
Tue 28 Mar 2017, 13:46 GMT

Quadrise confirms two-shift production at Cepsa refinery


Manufacturing unit at San Roque switched to 24-hour production in January.



Quadrise Fuels International plc has confirmed that production of its MSAR fuel at Cepsa's San Roque refinery in Spain moved to a two-shift production schedule in January - operating the MSAR Manufacturing Unit (MMU) on a 24-hour basis to produce the largest single batch of MSAR to date.

In its interim results for the last six months of the year, the UK firm said that production of MSAR during the period had "progressed well" and that incremental enhancements to the MMU were "proving to be helpful as we build up our operational experience within a refinery that processes a variety of different crude oils".

Quadrise noted that, since the start of the year, it has also been working with Cepsa to examine new opportunities to maximize the MSAR production capacity at the San Roque facility. Discussions are said to be "progressing well".

Maersk trial could resume in Q4 2017

Maersk is also said to be reviewing options to recommence and complete a 'letter of no objection (LONO) trial' on a new vessel from the fourth quarter of 2017 onwards. It follows Maersk's recent cancellation of the trial, which was confirmed by Quadrise earlier this month.

Last year, in July, following the installation of an MSAR manufacturing unit at the San Roque site, trials commenced with MSAR fuel from the refinery being supplied to and burnt by a nominated Maersk vessel on its regular scheduled route.

Maersk is cited by Quadrise as saying that the trial "progressed well"; however, operational issues with the trial vessel, said to be totally unrelated to MSAR, resulted in Quadrise making two announcements, on 2nd and 13th March respectively. The first of these announcements confirmed that there had been an incident that would require the trial vessel to undergo an unscheduled dry dock visit. The second announcement, on 13th March, stated that Quadrise had been advised by Maersk that it would not be possible for the trial to continue on the vessel following the dry dock visit as it would then be redeployed on a different service that would not permit further bunkering at Algeciras.

As a result, it was confirmed that the current trial on this vessel would be suspended once the remaining MSAR fuel on board had been consumed.

Quadrise also said on 13th March that Wartsila will be carrying out a detailed interim inspection of the trial vessel's engine to document the performance of MSAR fuel to date.

Wartsila LONO: the commercial trigger point

Whilst Quadrise still aims to start commercial operations in 2017, and to begin the commercial delivery of MSAR from the Cepsa refinery to an expanding number of Maersk ships, the company concedes that the suspension of Maersk's trial will have an impact on this timetable.

Quadrise says that for Maersk, a positive interim inspection and LONO by Wartsila is the trigger point for commencing commercial discussions.

"Maersk's decision will ultimately be taken on several factors, primarily economic and operational, that will include the economic and environmental advantages of MSAR in addition to their chosen approach to compliance with the new IMO open ocean sulphur standards that come into force in 2020," Quadrise noted.

In addition to its continuing discussions with Maersk, Quadrise says that it has also been increasing its activities with other shipping operators and that an interim LONO from Wartsila "will be a very positive attribute in progressing those activities".

"Alongside this, we will be continuing our discussions with a number of other producers in the major European and Asian bunker hubs and regional refining centres to provide additional sourcing opportunities," Quadrise added.

Financial results

In its financial results for the last six months of 2016, Quadrise posted a loss of GBP 2.4 million. The production and development costs for the period amounted to GBP 1.3 million, most of which related to the ongoing LONO trial with Maersk.

As at 31st December, Quadrise held cash and cash equivalents of GBP 7.0 million. This includes GBP 5.0 million (net of costs) raised through a placing and open offer during the period.


IBIA MFM bunkering training course graphic. IBIA announces new date for mass flow meter training course in Rotterdam  

Training scheduled for 12 May follows mandatory MFM implementation at Rotterdam and Antwerp-Bruges ports.

A Maersk vessel, pictured from above. Maersk and Hapag-Lloyd suspend Strait of Hormuz transits amid Middle East security crisis  

Container carriers reroute services around the Cape of Good Hope as military conflict escalates.

Map of Middle East. Operations continue as normal at most Middle East ports  

Most facilities operating normally, with exceptions in Bahrain, Oman and Saudi Arabia.

Photograph of the 93,000-cbm very large ammonia carrier (VLAC) Gaz Ronin. Naftomar takes delivery of 93,000-cbm dual-fuel ammonia carrier  

Gaz Ronin features a MAN dual-fuel engine with high-pressure selective catalytic reduction technology.

Aurora Botnia leaving harbor. AYK Energy completes world’s largest marine battery retrofit on Wasaline ferry  

Aurora Botnia receives 10.4 MWh battery system, bringing total capacity to 12.6 MWh.

Steel cutting ceremony for an LNG dual-fuel 307,000-tonne crude oil tanker with builder's hull no. 113. Dalian Shipbuilding begins construction on LNG dual-fuel crude tanker  

Development is one of a number of milestones reported by parent company over the past few days.

Photograph of Sallaum Lines' Ocean Breeze vessel with 'Introducing The Blue Corridor' overlaid text. Sallaum Lines launches Blue Corridor sustainability initiative for Europe–Africa ro-ro trade  

Company deploys LNG-capable vessels with AI routing and eco-speed protocols on new green shipping corridor.

The platform supply vessel Viking Energy. Eidesvik Offshore signs yard contract for ammonia retrofit of PSV Viking Energy  

Halsnøy Dokk to convert platform supply vessel as part of EU-backed Apollo project.

Vanquish tanker alongside Jette Theresa oil/chemical tanker docked at terminal. North Sea Port completes risk analysis for alternative fuel bunkering operations  

Port authority says LNG, hydrogen, methanol and ammonia can be safely refuelled across its facilities.

Container ship near a port. Ammonia emerges as most feasible alternative fuel for deep-sea shipping in 2050 emissions study  

Research combining expert survey and technical analysis ranks ammonia ahead of hydrogen and methanol.


↑  Back to Top


 Recommended