This is a legacy page. Please click here to view the latest version.
Tue 28 Mar 2017, 13:46 GMT

Quadrise confirms two-shift production at Cepsa refinery


Manufacturing unit at San Roque switched to 24-hour production in January.



Quadrise Fuels International plc has confirmed that production of its MSAR fuel at Cepsa's San Roque refinery in Spain moved to a two-shift production schedule in January - operating the MSAR Manufacturing Unit (MMU) on a 24-hour basis to produce the largest single batch of MSAR to date.

In its interim results for the last six months of the year, the UK firm said that production of MSAR during the period had "progressed well" and that incremental enhancements to the MMU were "proving to be helpful as we build up our operational experience within a refinery that processes a variety of different crude oils".

Quadrise noted that, since the start of the year, it has also been working with Cepsa to examine new opportunities to maximize the MSAR production capacity at the San Roque facility. Discussions are said to be "progressing well".

Maersk trial could resume in Q4 2017

Maersk is also said to be reviewing options to recommence and complete a 'letter of no objection (LONO) trial' on a new vessel from the fourth quarter of 2017 onwards. It follows Maersk's recent cancellation of the trial, which was confirmed by Quadrise earlier this month.

Last year, in July, following the installation of an MSAR manufacturing unit at the San Roque site, trials commenced with MSAR fuel from the refinery being supplied to and burnt by a nominated Maersk vessel on its regular scheduled route.

Maersk is cited by Quadrise as saying that the trial "progressed well"; however, operational issues with the trial vessel, said to be totally unrelated to MSAR, resulted in Quadrise making two announcements, on 2nd and 13th March respectively. The first of these announcements confirmed that there had been an incident that would require the trial vessel to undergo an unscheduled dry dock visit. The second announcement, on 13th March, stated that Quadrise had been advised by Maersk that it would not be possible for the trial to continue on the vessel following the dry dock visit as it would then be redeployed on a different service that would not permit further bunkering at Algeciras.

As a result, it was confirmed that the current trial on this vessel would be suspended once the remaining MSAR fuel on board had been consumed.

Quadrise also said on 13th March that Wartsila will be carrying out a detailed interim inspection of the trial vessel's engine to document the performance of MSAR fuel to date.

Wartsila LONO: the commercial trigger point

Whilst Quadrise still aims to start commercial operations in 2017, and to begin the commercial delivery of MSAR from the Cepsa refinery to an expanding number of Maersk ships, the company concedes that the suspension of Maersk's trial will have an impact on this timetable.

Quadrise says that for Maersk, a positive interim inspection and LONO by Wartsila is the trigger point for commencing commercial discussions.

"Maersk's decision will ultimately be taken on several factors, primarily economic and operational, that will include the economic and environmental advantages of MSAR in addition to their chosen approach to compliance with the new IMO open ocean sulphur standards that come into force in 2020," Quadrise noted.

In addition to its continuing discussions with Maersk, Quadrise says that it has also been increasing its activities with other shipping operators and that an interim LONO from Wartsila "will be a very positive attribute in progressing those activities".

"Alongside this, we will be continuing our discussions with a number of other producers in the major European and Asian bunker hubs and regional refining centres to provide additional sourcing opportunities," Quadrise added.

Financial results

In its financial results for the last six months of 2016, Quadrise posted a loss of GBP 2.4 million. The production and development costs for the period amounted to GBP 1.3 million, most of which related to the ongoing LONO trial with Maersk.

As at 31st December, Quadrise held cash and cash equivalents of GBP 7.0 million. This includes GBP 5.0 million (net of costs) raised through a placing and open offer during the period.


TFG Marine mass flow meter (MFM). TFG Marine fits two more US Gulf Coast barges with certified mass flow meters  

TFG Marine expands its mass flow meter rollout on the US Gulf Coast, adding ISO 22192 certification to two supply barges.

Hercules Vanessa vessel. HTM’s Hercules Vanessa begins maiden voyage as Ultra-Spec tanker series expands  

Vessel is the latest addition to Hercules Tanker Management’s 10-ship next-generation fleet renewal programme.

Steel-cutting ceremony for TRAnsverse 2600e vessels. Cochin Shipyard begins construction of Svitzer’s battery-electric tugs in India  

Four TRAnsverse 2600e vessels are claimed to be among the most advanced green tugs under construction globally.

TT-Line Green Ship 2.0 illustration. MacGregor wins ro-ro equipment contract for TT-Line’s battery-hybrid LNG ferries  

Company to supply cargo handling systems for two new LNG-powered ferries destined for Baltic Sea routes.

IAEA ATLAS initiative launch. Nuclear-powered commercial shipping moves closer to reality after Washington summit  

IAEA launches ATLAS initiative to tackle regulatory and commercial barriers to maritime nuclear deployment.

Vessels equipped with K-Sail render. Norwegian consortium launches WINTEGRATE project to advance wind-assisted ship propulsion  

A NOK 68m research initiative aims to integrate wind propulsion with onboard ship systems.

Ro-Pax ferry render. ABB wins power, propulsion and automation contract for New Zealand’s new Cook Strait ferries  

Two new ro-pax ferries featuring Azipod propulsion will operate the Wellington–Picton crossing from 2029.

Everllence ME-LGIMe engine render. Everllence completes R&D testing for world's first ethanol-powered very large ore carrier engine  

G80 tri-fuel engine is bound for a Vale-chartered ore carrier, with delivery set for early 2027.

Auramarine team. Flexibility, not fuel choice, is key to energy transition, says Auramarine  

Finnish fuel supply systems company argues adaptability now outweighs commitment to any single fuel.

Way Forward render. Wallenius to fit wing sails on car carrier in first commercial wind propulsion step  

Two wing sails ordered for installation on vessel said to already hold the top CII rating.


↑  Back to Top