Thu 18 Oct 2012 16:54

Singapore LNG terminal nearing completion


City-state's first LNG facilility on Jurong Island is said to be close to completion.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be close to completion.

In its latest update on the construction project, SLNG said that the terminal facility was 95 percent completed and that there had been good progress on LNG Tanks 1 & 2, where hydrotesting had been carried out and the temporary wall openings closed.

Installation of the perlite insulation between the inner and outer wall of Tank 1 has started. On Tank 3, erection of the inner nickel steel tank wall is 50 percent completed.

Progress is also said to have been made on the sea water intake; the major civil works have been completed, equipment installed and the sheet piles removed to allow erection of the sea water filters.

Piping works are expected to be completed by the end of October and equipment installation is reaching completion. Electrical/ instrumentation cable pulling and termination works are said to be well underway.

According to SLNG, progress on the Secondary Berth have reached 33 percent, with piling for the tertiary jetty completed. The main quay wall and its tie-back system have been installed and dredging of the secondary berth area is underway.

EPC contractor Samsung C&T has increased the site workforce to approximately 2,800 staff. To date, more than 9 million hours have been worked on the LNG Terminal project without any lost time injury, SLNG said.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business, i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Marius Kairys, CEO of Elenger Sp. z o.o. Elenger enters Polish LNG bunkering market with ferry refuelling operation  

Baltic energy firm completes maiden truck-to-ship LNG delivery in Gdansk.

Samsung Heavy Industries (SHI) virtual reality (VR) training program developed in collaboration with Evergreen. SHI develops VR training solutions for Evergreen's methanol-fuelled ships  

Shipbuilder creates virtual reality program for 16,500 TEU boxship operations.

Illustratic image of Itochu's newbuild ammonia bunkering vessel, scheduled for delivery in September 2027. Itochu orders 5,000 cbm ammonia bunker vessel  

Japanese firm targets Singapore demonstration after October 2027, with Zeta Bunkering lined up to perform deliveries.

Bunkering of the Glovis Selene car carrier. Shell completes first LNG bunkering operation with Hyundai Glovis in Singapore  

Energy major supplies fuel to South Korean logistics firm's dual-fuel vessel.

Orient Overseas Container Line (OOCL) vessel. CPN delivers first B30 marine gasoil to OOCL in Hong Kong  

Chimbusco Pan Nation claims to be first in region to supply all grades of ISCC-EU certified marine biofuel.

The Buffalo 404 barge, owned by Buffalo Marine Service Inc., performing a bunker delivery. TFG Marine installs first ISO-certified mass flow meter on US Gulf bunker barge  

Installation marks expansion of company's digitalisation programme across global fleet.

Sogestran's fuel supply vessel, the Anatife, at the port of Belle-Île-en-Mer. Sogestran's HVO-powered tanker achieves 78% CO2 reduction on French island fuel runs  

Small tanker Anatife saves fuel while supplying Belle-Île and Île d'Yeu.

Crowley 1,400 TEU LNG-powered containership, Tiscapa. Crowley deploys LNG-powered boxship Tiscapa for Caribbean and Central American routes  

Vessel is the third in company's Avance Class fleet to enter service.

The inland LNG bunker vessel LNG London. LNG London completes 1,000 bunkering operations in Rotterdam and Antwerp  

Delivery vessel reaches milestone after five years of operations across ARA hub.

The M.V. COSCO Shipping Yangpu, China's first methanol dual-fuel containership. COSCO vessel completes maiden green methanol bunkering at Yangpu  

China's first methanol dual-fuel containership refuels with green methanol derived from urban waste.


↑  Back to Top