Thu 18 Oct 2012, 16:54 GMT

Singapore LNG terminal nearing completion


City-state's first LNG facilility on Jurong Island is said to be close to completion.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be close to completion.

In its latest update on the construction project, SLNG said that the terminal facility was 95 percent completed and that there had been good progress on LNG Tanks 1 & 2, where hydrotesting had been carried out and the temporary wall openings closed.

Installation of the perlite insulation between the inner and outer wall of Tank 1 has started. On Tank 3, erection of the inner nickel steel tank wall is 50 percent completed.

Progress is also said to have been made on the sea water intake; the major civil works have been completed, equipment installed and the sheet piles removed to allow erection of the sea water filters.

Piping works are expected to be completed by the end of October and equipment installation is reaching completion. Electrical/ instrumentation cable pulling and termination works are said to be well underway.

According to SLNG, progress on the Secondary Berth have reached 33 percent, with piling for the tertiary jetty completed. The main quay wall and its tie-back system have been installed and dredging of the secondary berth area is underway.

EPC contractor Samsung C&T has increased the site workforce to approximately 2,800 staff. To date, more than 9 million hours have been worked on the LNG Terminal project without any lost time injury, SLNG said.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business, i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Durban container port. Consortium reaffirms plans for Durban project that could provide LNG bunkering  

Infrastructure developed could be used to offer LNG bunkering services at the South African port.

Steel-cutting ceremony for vessel with builder's hull no. S1161. CIMC SOE begins construction of 18,900-cbm LNG bunkering vessel for Spanish owner  

Vessel to feature 'ultra-low methane slip engine' and high-storage-pressure design.

Morten Lysvold Nilsen and Jon Torvald Havardsen. Breeze Ship Design, Bjòrn Shipping and Norse Shipyard team up on new aquaculture support vessel  

Vessel to be equipped with battery system intended to help reduce fuel consumption and emissions.

World Shipping Council logo. World Shipping Council pushes for binding global emissions rules as fleet investment tops $200bn  

Trade body warns delays to IMO's climate framework risk stalling progress on the investment already committed to dual-fuel vessels.

Person signing a contract. K Line orders two LPG dual-fuel VLGCs designed for ammonia carriage  

Kawasaki Kisen Kaisha signs deal with HD Hyundai Samho for two gas carriers able to run on LPG, with delivery due in 2030.

OOCL Grace ship-to-ship (STS) bunkering operation at Shenzhen Port. OOCL Grace completes 'green methanol bunkering' during YICT maiden call  

Second of seven dual-fuel OOCL container vessels carries out methanol bunkering during first visit to container-terminal complex.

Tokyo skyline. Monjasa opens recruitment for trading role in Tokyo  

Position requires minimum of three to four years of relevant experience in the bunker or shipping industry.

Terra Clove crew following successful sea trials. Eastern Pacific Shipping's Terra Clove runs on ammonia in maiden voyage  

Terra Clove, described as the world's first commercial ammonia dual-fuel VLAC, is operating at sea following trials.

Samsung Heavy Industries (SHI) and Tesser Atomics sign MoU. Tesser Atomics and Samsung Heavy Industries agree exclusive deal on nuclear-powered LNG carrier  

Partners plan demonstration vessel using a fluoride-salt-cooled reactor for transatlantic LNG trade routes.

Fincantieri logo. Fincantieri secures order for two LNG dual-fuel cruise ships from Carnival  

Carnival Corporation orders two dual-fuel, LNG-powered cruise ships from Fincantieri for delivery in 2033 and 2035.