Thu 18 Oct 2012, 16:54 GMT

Singapore LNG terminal nearing completion


City-state's first LNG facilility on Jurong Island is said to be close to completion.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be close to completion.

In its latest update on the construction project, SLNG said that the terminal facility was 95 percent completed and that there had been good progress on LNG Tanks 1 & 2, where hydrotesting had been carried out and the temporary wall openings closed.

Installation of the perlite insulation between the inner and outer wall of Tank 1 has started. On Tank 3, erection of the inner nickel steel tank wall is 50 percent completed.

Progress is also said to have been made on the sea water intake; the major civil works have been completed, equipment installed and the sheet piles removed to allow erection of the sea water filters.

Piping works are expected to be completed by the end of October and equipment installation is reaching completion. Electrical/ instrumentation cable pulling and termination works are said to be well underway.

According to SLNG, progress on the Secondary Berth have reached 33 percent, with piling for the tertiary jetty completed. The main quay wall and its tie-back system have been installed and dredging of the secondary berth area is underway.

EPC contractor Samsung C&T has increased the site workforce to approximately 2,800 staff. To date, more than 9 million hours have been worked on the LNG Terminal project without any lost time injury, SLNG said.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business, i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Fuel for Thought: LPG report. Lloyd’s Register examines LPG as marine fuel in new research report  

Classification society evaluates LPG emissions benefits, safety considerations and technology readiness for shipping.

Steel-cutting ceremony for vessel with builder's hull no. W0284. Finnlines begins construction of first methanol-capable ro-pax vessel in EUR 500m newbuild programme  

Grimaldi Group subsidiary begins work on Hansa Superstar class ships at Chinese shipyard.

Navios Cyan vessel. Navios Partners takes delivery of LNG- and methanol-ready boxship  

The 7,900-teu Navios Cyan is the first of four newbuildings in the series.

Rendering of a hydrogen energy system. Floating hydrogen power hub validated for grid-independent ship charging at berth  

ELIRE Maritime-led consortium validates modular platform delivering 5MW of clean power without a shoreside grid connection.

Kota Ocean ship-to-ship (STS) LNG bunkering operation. PIL completes first LNG bunkering at Shanghai’s Mingdong Terminal  

Kota Ocean took on 4,300-cbm of LNG during simultaneous cargo operations.

Fully electric passenger ferry render. Estonia orders first fully electric ferry from Polish shipyard CRIST  

Battery-powered vessel designed by LMG Marin will operate on the Virtsu–Kuivastu route from 2028.

Eco Levant vessel. X-Press Feeders trials ethanol-methanol blend in Rotterdam  

Container operator tests 10-90 ethanol-methanol fuel mix aboard Eco Levant vessel.

Venture Energy, CSST and CSTC MoU signing. Venture Energy signs green methanol cooperation agreement  

MoU establishes framework for long-term offtake and capacity development in maritime decarbonisation.

Iberdrola España Onshore Power Supply (OPS). Iberdrola España completes shore power installation at the Port of Pasaia  

Spanish utility installs onshore power supply system, enabling docked vessels to use renewable electricity.

Illustratic image of Itochu's newbuild ammonia bunkering vessel, scheduled for delivery in September 2027. Itochu secures approval for ammonia bunkering trials in Singapore  

Japanese trading house to conduct two-year trial following MPA authorisation.