Mon 15 Dec 2014, 17:34 GMT

LNG storage tank construction 'progressing well'


Update on the progress of LNG tank storage projects in Indonesia and the Philippines.



Gaztransport & Technigaz (GTT), a leading designer of membrane containment systems for the maritime transportation and storage of liquefied natural gas (LNG), says the construction of two LNG storage tanks ordered by Energy World Corporation (EWC) in Southeast Asia is "progressing well".

In 2009 and 2011, Energy World Corporation (EWC) and GTT signed two contracts for land storage tank construction in Indonesia and the Philippines, to be equipped with GTT's GST® Membrane Full Integrity System. For both projects, GTT is supervising the detailed design of the storage tank containment systems, provides technical assistance on site during the containment systems installation and is to assist the operator during the whole tank life.

The first project between EWC and GTT is the Sengkang LNG site development project in Keera, Indonesia. So far, the walls of the 88,000-cubic-metre tank have been completed since the summer and the roof installation is to "start soon", according to GTT. Installation of containment system is planned for beginning of 2015.

The second construction project - a 130,000-cubic-metre LNG storage tank - is being built for LNG Hub Terminal on Pagbilao Grande Island, Quezon Province, in the Philippines.

"Both projects are progressing in parallel, and, as for Sengkang, the containment system is planned for beginning of next year," GTT said in a statement.

Stewart W. G. Elliott, chairman, managing director and chief executive officer of EWC, said that it was "a significant construction step for the Philippines' first LNG receiving terminal and for the Indonesian liquefaction plant".

Philippe Berterottière, President & CEO of GTT remarked that the two projects were "significant first steps" on the return of GTT membrane type land storage systems to the world market.

"These projects both benefit from the inherent cost and schedule advantages of the GTT design," GTT added.


Sing Fuels logo. Sing Fuels seeks Asia-based supply trader to bolster bunker procurement team  

Singapore bunkering firm is recruiting a supply trader to manage marine fuel purchasing across Asia.

MOL joint naming ceremony. MOL names world's first ammonia-fuelled Capesize bulk carriers  

Naming of Ruri Mirai, Ruri Sekai and Ruri Hikari signals ammonia's arrival as a marine fuel for large bulk carriers.

Washington State Hybrid-Electric 160-Auto Ferry vessel render. ABB wins Washington State Ferries' third hybrid-electric vessel order  

ABB extends its role in the US ferry operator's electrification programme, which targets emission-free operations by 2050.

Aurora Borealis vessel. Kawasaki Heavy Industries delivers LPG-fuelled carrier Aurora Borealis  

Ship could also be modified in future to allow for ammonia-fuelled operation.

Rendering of Estonia's first shore-charged electric ferry. Estonian State Fleet's shore-charged electric ferry completes model testing in Germany  

Hull and propulsion tests show the vessel's energy consumption remains within contracted limits with room to spare.

Kypros Island vessel. Tsuneishi delivers first methanol dual-fuel Kamsarmax bulk carrier from Chinese yard  

Shipbuilder claims progress towards establishing a mass-production system for vessels designed to reduce environmental impact.

ZIM LNG container vessel. Los Angeles and Long Beach identify LNG and methanol as key near-term marine fuels  

Joint feasibility study maps out demand projections and infrastructure needs to support cleaner shipping fuels at San Pedro Bay

Alexander Treff, Christiania Energy, Christiania Energy welcomes student assistant to Copenhagen office  

Alexander Treff joins marine fuels firm while studying international business at Copenhagen Business School.

Carlotta Cosulich vessel. Cosulich Marine Energy takes delivery of third methanol-ready bunker tanker  

Carlotta Cosulich joins the group’s fleet, bringing its four-vessel bunkering programme closer to completion.

Rendering of a Wallenius Wilhelmsen vessel Wallenius Wilhelmsen orders four dual-fuel PCTCs, extends fleet renewal programme  

Shipping firm signs for LNG-fuelled car carriers with options for eight more, with deliveries from 2030.