This is a legacy page. Please click here to view the latest version.
Mon 24 Sep 2012, 08:11 GMT

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Nicklas Mikkelsen, Malik Supply. Malik Supply hires first trader for new Dubai office  

Nicklas Mikkelsen joins Danish bunker supplier ahead of January 2026 launch.

Tallink’s MyStar vessel. Tallink's MyStar joins Gasum's FuelEU Maritime compliance pool using bio-LNG  

Nordic energy company Gasum signs pooling agreement with Elenger to generate compliance surplus.

Methane Abatement in Maritime Innovation Initiative (MAMII) speakers. Maritime coalition gathers in Brussels to advance methane measurement and abatement technologies  

MAMII convenes shipowners, engine makers, and policymakers to accelerate methane reduction from LNG-fueled vessels.

Green oil bubbles. BIMCO delays biofuel clause for time charters to spring 2026  

Maritime organisation pushes back publication to address safety, technical requirements, and industry feedback.

Group photo of participants at the REMPEC expert meeting. Mediterranean moves closer to nitrogen oxide emission controls  

Expert meeting endorses feasibility study with 2032 target for Med NOx ECA implementation.

Seaboard Venture naming ceremony. Sanfu Shipbuilding delivers final 3,500 TEU dual-fuel container ship to US owner  

Taizhou-based shipyard completes first batch of LNG-powered vessels with "zero accidents, zero delays".

Aerial view of a container vessel. FuelEU Maritime regulation reshapes ship management contracts, DNV says  

DNV's Emissions Connect aims to provide neutral data for commercial negotiations under new rules.

Illustration of Scales of Justice with cargo ship and penalty block. FuelEU penalties spark contract disputes as first-year compliance costs emerge  

Shipowners and charterers negotiate biofuel handling, payment timing, and multiplier penalties under new regulations.

Marina Bay Sands, Singapore. Singapore tops first global container port ranking by DNV and Menon Economics  

The port leads across all five assessment pillars in inaugural industry report.

Jack Spyros Pringle, Lloyd’s Register. Marine fuel procurement becomes strategic imperative as regulatory pressures mount: LR  

Operators must adopt comprehensive fuel strategies amid supply constraints and compliance costs, says Lloyd's Register.


↑  Back to Top


 Recommended