This is a legacy page. Please click here to view the latest version.
Mon 24 Sep 2012 08:11

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Product tanker Artizen, owned by Hong Lam Marine. Hong Lam Marine takes delivery of Artizen tanker in Japan  

Singapore-based firm receives new vessel from Kegoya Shipyard.

Birdseye view of containership. Panama Canal launches NetZero Slot to incentivize low-emission transits  

New reservation category prioritizes dual-fuel vessels capable of using alternative fuels from November.

Van Oord's Vox Apolonia. Van Oord deploys bio-LNG dredger for Dutch coastal project  

First bio-LNG powered trailing suction hopper dredger operation begins in the Netherlands.

Model testing for Green Handy methanol-powered vessel. Methanol-fuelled Green Handy ships pass model tests ahead of 2026 construction  

Baltic carrier reports model testing exceeded performance targets for 17,000 dwt methanol-powered vessels.

Miguel Hernandez and Olivier Icyk at AiP for FPSO. SBM Offshore's floating ammonia production design gets ABS approval  

Design converts offshore gas to ammonia while capturing CO2 for maritime and power sectors.

Philippe Berterottière and Matthieu de Tugny. GTT unveils cubic LNG fuel tank design for boxships with BV approval  

New GTT CUBIQ design claims to reduce construction time and boost cargo capacity.

Wilhelmshaven Express, Hapag-Lloyd. Hapag-Lloyd secures multi-year liquefied biomethane supply deal with Shell  

Agreement supports container line's decarbonisation strategy and net-zero fleet operations target by 2045.

Dual-fuel ship. Dual-fuel vessels will dominate next decade, says Columbia Group  

Ship manager predicts LNG-powered vessels will bridge gap until zero-carbon alternatives emerge.

Stril Poseidon vessel. VPS campaign claims 12,000 tonnes of CO2 savings across 300 vessels  

Three-month efficiency drive involved 12 shipping companies testing operational strategies through software platform.

Birdseye view of a ship. Gard warns of widespread cat fines surge in marine fuel  

Insurer reports elevated contamination levels, echoing VPS circular in early September.


↑  Back to Top


 Recommended