This is a legacy page. Please click here to view the latest version.
Mon 24 Sep 2012, 08:11 GMT

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Aerial view of container vessel at sea. Seaspan and Technolog unveil LNG feeder design with four-week ammonia conversion pathway  

Lloyd’s Register grants approval for a 3,370 TEU vessel concept designed for swift transition to zero-carbon fuel.

David Foo, MPA. Singapore’s MPA backs LNG as part of multi-fuel strategy for shipping decarbonisation  

Authority emphasises regulatory frameworks and workforce development as sector navigates geopolitical uncertainty and energy transition.

ABS and PIL sign MoU. ABS and PIL partner on book-and-claim emissions verification  

Classification society to verify fuel consumption and emissions data for shipping line’s alternative fuel claims.

Biofuel bunkering at Port of Açu. Vast completes first biofuel bunkering of tugboat at Brazil’s Port of Açu  

Be8’s BeVant biofuel claims up to 99% CO₂ reduction versus conventional marine diesel.

China’s Da Qing 268 vessel. Ningbo-Zhoushan Port completes first ship-to-ship green methanol bunkering  

Zhejiang province port facility delivered 503 tonnes of methanol to a container ship in one hour.

Ole Sloth Hansen and Arne Lohmann Rasmussen. KPI OceanConnect launches podcast series on bunker markets and geopolitical risk  

Marine fuel supplier debuts audio series examining commodity markets, trade route disruptions and Middle East tensions.

Auramarine biofuels webinar. Auramarine to host webinar on biofuels as a marine decarbonisation solution  

Finnish firm's May event will explore current biofuel options and integration strategies for vessels.

Thomas Bondesen, Christian Ramsdal and Jeanette Rathje, Malik Group. Malik adds bunker trader, technology head and canteen worker  

Danish marine fuels group expands team with three appointments across commercial, technical and operational functions.

Marine Money 2026 forum. AET outlines multi-fuel decarbonisation strategy at Marine Money 2026  

Tanker operator highlights innovative commercial arrangements with charterers to share decarbonisation risks and rewards.

Titan Optimus alongside Peony Leader vessel. Titan Clean Fuels completes first FuelEU Maritime pooling exercise with DNV verification  

Pool included several hundred vessels, with LNG and biomethane helping balance compliance deficits.


↑  Back to Top