This is a legacy page. Please click here to view the latest version.
Mon 24 Sep 2012, 08:11 GMT

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Illustration of balance scale with cargo ship and penalty block. FuelEU penalties spark contract disputes as first-year compliance costs emerge  

Shipowners and charterers negotiate biofuel handling, payment timing, and multiplier penalties under new regulations.

Marina Bay Sands, Singapore. Singapore tops first global container port ranking by DNV and Menon Economics  

The port leads across all five assessment pillars in inaugural industry report.

Jack Spyros Pringle, Lloyd’s Register. Marine fuel procurement becomes strategic imperative as regulatory pressures mount: LR  

Operators must adopt comprehensive fuel strategies amid supply constraints and compliance costs, says Lloyd's Register.

Xinfu124 ultra-large LNG carrier. Private Chinese shipbuilder plans to deliver eight dual-fuel boxships  

Yangzi Xinfu is fully booked until May 2029 and expected to post annual sales revenue exceeding $1.4 billion.

Østensjø Rederi newbuild tug render. Østensjø Rederi orders methanol-ready tug from Spanish shipyard  

Norwegian operator contracts Astilleros Gondán for vessel with diesel-electric hybrid propulsion system.

Bound4blue worker in safety gear. Bound4blue establishes China production base for wind propulsion systems  

Spanish wind propulsion firm targets Asian shipbuilding market with outsourced manufacturing network.

Alfa Laval and Hanwha Ocean Ecotech sign MoU. Alfa Laval and Hanwha Ocean Ecotech partner on ammonia fuel systems  

Collaboration aims to develop ammonia fuel technology for dual-fuel vessels in the Asian market.

Meg Dowling, Lloyd's Register. Nuclear-powered boxships could deliver $68m annual savings: Lloyd's Register  

Small modular reactors could eliminate fuel costs and carbon penalties while boosting cargo capacity, says report.

Minerva Bunkering and Autoridad Portuaria de Las Palmas (APLP) signing ceremony. Minerva Bunkering extends Las Palmas terminal concession by 15 years  

Bunker supplier adds barge capacity and explores new terminal for energy transition fuels.

Liam Blackmore, Lloyd's Register. Ammonia Energy Association releases gas detection whitepaper with Lloyd's Register input  

Lloyd's Register contributed expertise to new guidance on ammonia detection systems for the maritime sector.


↑  Back to Top


 Recommended