This is a legacy page. Please click here to view the latest version.
Mon 24 Sep 2012, 08:11 GMT

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Person signing a document. Venture Energy signs green methanol supply deal with Shenji Energy  

Hong Kong-based firm to purchase ISCC EU-certified biomass-derived methanol for shipping clients.

Steel cutting ceremony of vessel with builder's hull no. CHB2060. Changhong International begins construction on second 11,400-teu LNG dual-fuel container ship  

Chinese shipbuilder starts work on vessel CHB2060, second of 18-ship series for Oceanroutes.

Keel-laying ceremony of Celsius. Keel laid for LNG bunkering vessel Celsius  

Turkish shipbuilder begins construction of dual-fuel bunkering vessel for Sirius Shipping and Gasum.

Marine ISTA alongside MSC Apollo vessel. Vitol’s Marine ISTA completes record 4,900 mt bunkering operation at Karachi Port  

Operation marks largest fuel supply at Pakistani port, highlighting potential for regional bunkering hub development.

Aurora Botnia vessel. Gasum and Wasaline extend bio-LNG supply agreement to 2027  

Nordic energy company renews fuel supply contract with Finnish-Swedish ferry operator through 2027.

Luminara vessel truck-to-ship bunkering. MOL Techno-Trade completes Japan’s first truck-to-ship LNG bunkering for foreign cruise vessel  

Ritz-Carlton cruise ship Luminara refuelled at Nagasaki Port using truck-to-ship method on 3 April.

NKT Eleonora vessel cable-laying. Methanol-ready cable-laying vessel hull launched in Romania  

Shipbuilder floats hull of dual-fuel vessel designed for offshore renewable energy cable operations.

Dr Prapisala Thepsithar, GCMD. GCMD biofuels lead receives Singapore standardisation award  

Dr Prapisala Thepsithar recognised for contributions to marine biofuel specification development.

Marine Energy Wales (MEW) Conference 2026 graphic. Certas Energy to attend Marine Energy Wales conference in April  

Marine fuel supplier to discuss sector solutions at UK marine renewable energy conference.

Dinamo IV vessel. Sanmar completes sea trials for 14th all-electric tugboat  

Turkish shipyard marks half-century in business with latest battery-powered vessel from ElectRA series.


↑  Back to Top