This is a legacy page. Please click here to view the latest version.
Mon 24 Sep 2012, 08:11 GMT

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Steel cutting ceremony of vessel with builder's hull no. CHB2059. Changhong International begins construction of first 11,400-teu LNG dual-fuel boxship for Oceanroutes  

Chinese yard starts work on first of 18 vessels in order from new customer.

Wee Meng Tan, GCMD. China’s renewable energy could fuel global shipping decarbonisation, says GCMD  

Maritime body sees potential for China to convert domestic wind and solar into green marine fuels.

OceanScore logo. OceanScore adds vessel activation controls for EU ETS and FuelEU compliance workflows  

Software provider introduces a feature allowing third-party managers to toggle vessel compliance status while preserving historical data.

Mitsui O.S.K. Lines (MOL) logo. MOL develops carbon inset and book-and-claim programme for alternative marine fuels  

Japanese shipowner details mechanism to verify, certify and fund use of biomethanol and other low-carbon fuels.

Deck view of Hafnia Larvik at sea. Hafnia orders eight MR tankers from Hyundai Heavy Industries for $405m  

Vessels scheduled for delivery between Q3 2028 and Q2 2029 at South Korean shipyard.

Sommer Mitchel, IBIA. IBIA appoints Sommer Mitchell as marketing and events coordinator  

Mitchell brings more than five years of experience to the marine fuels industry association.

Lazulite Ace vessel. MOL's 12th LNG dual-fuel car carrier makes maiden call in Singapore  

Lazulite Ace arrives in Singapore following delivery from Japanese shipyard in March.

Methanol bunkering demonstration at Kandla. Deendayal Port Authority completes India’s first methanol bunkering demonstration  

Kandla port conducts maiden methanol bunkering trial in 'step towards maritime decarbonization.'

Keel-laying ceremony of Viking Astrea. Fincantieri lays keel for hydrogen-powered cruise ship Viking Astrea  

Second hydrogen-fuelled vessel in Viking series scheduled for delivery in 2027 from Ancona yard.

T. Florya vessel. RMK Marine launches methanol-ready chemical tanker for Ditaş Denizcilik  

T. Florya, a 12,000-dwt vessel designed by Delta Marine, is launched by Turkish shipbuilder.


↑  Back to Top