This is a legacy page. Please click here to view the latest version.
Mon 24 Sep 2012, 08:11 GMT

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Jurgen Gerdes, WinGD. WinGD signs global service agreement for TMS Cardiff Gas LNG carrier newbuilds  

WinGD will support six dual-fuel engines on three new LNG carriers for the Athens-based operator throughout their operational lives.

Yangze LNG 01 vessel. Yangzijiang Xinfu delivers first 175,000-cbm LNG carrier built by Chinese private shipyard  

Vessel features two dual-fuel MAN B&W 5G70ME-C10.5-GA-EGR engines fitted with cryogenic units.

Kaguya 200th ship-to-ship (STS) LNG bunkering operation. LNG bunkering vessel Kaguya completes 200th ship-to-ship operation in Japan  

K Line’s joint venture vessel reaches milestone in Mikawa Bay.

MFM Nicole vessel. Synergy Marine adds dual-fuel LPG carrier to managed fleet  

MFM Nicole joins Synergy’s gas carrier portfolio as owners weigh fuel choices ahead of MEPC 85 negotiations.

CMA CGM Notre Dame vessel. DSV to use CMA CGM’s ACT+ solution to slash shipping emissions  

Danish firm targets 12,000-tonne reduction in CO₂ emissions over two years through the use of UCOME-based biofuels.

Peninsula 2026 graduate cohort. Peninsula welcomes 2026 graduate cohort across global bunkering network  

Bunker firm brings new graduates into roles spanning Houston, Singapore, Gibraltar, Monaco and Las Palmas.

Mathias Krogsgard, Malik Supply. Malik Supply appoints Mathias Krogsgård as bunker trader  

Danish bunker firm adds trader with export and technology background to growing team.

Jeroen De Vos, Peninsula. Biofuel adoption in shipping shifts from debate to delivery, says Peninsula's Jeroen de Vos  

Marine biofuels have moved from pilot projects to routine fuel strategy, argues IBIA vice-chair.

KEPCO E&C and KR signing. KEPCO E&C and Korean Register of Shipping to collaborate on marine SMR development  

Korean firms to develop technical standards and certification pathways for the BANDI offshore small modular reactor.

Ship-to-ship (STS) LNG bunkering operation at the Port of Sagunto. Peninsula completes first LNG bunkering operation at Sagunto  

Levante LNG bunkering vessel supplies K Line car carrier in landmark delivery.


↑  Back to Top