This is a legacy page. Please click here to view the latest version.
Mon 24 Sep 2012, 08:11 GMT

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Rolls-Royce mtu engine test bench. Rolls-Royce Power Systems switches German engine test facilities to HVO fuel  

Company saved 3,200 tonnes of CO2 by end of 2025 after switching to renewable diesel.

MSC Migsan delivery ceremony. Changhong International delivers final LNG dual-fuel container ship 205 days early  

Chinese shipbuilder completes 10-vessel series for MSC with delivery of 11,500-teu MSC Migsan.

Seoul city skyline. Oilmar seeks senior and mid-level bunker traders in Seoul  

Marine fuel firm aims to recruit experienced traders for South Korean operations.

Morten Thomas Jacobsen, GEA. Global Ethanol Association to present on ethanol marine fuel at London shipping expo  

Morten Thomas Jacobsen will discuss ethanol fuel trials and maritime decarbonisation challenges in June.

Adrian Tolson, IBIA. IBIA warns of structural shift in marine fuel market following Middle East tensions  

Association chair says geopolitical disruptions signal lasting changes to bunker supply dynamics and pricing.

HMM Hamburg vessel. Rotterdam bunker volumes plunge 25% in first quarter amid regulatory shifts  

Fossil fuel sales decline sharply while alternative fuels show modest growth in Dutch port.

Camellia Dream vessel. Norsepower completes factory tests for 18 rotor sails bound for Airbus fleet  

Wind propulsion units cleared for installation on LD Armateurs vessels targeting 50% emissions reduction.

Frankie Russ vessel. Ernst Russ acquires four chemical tankers with five-year charters worth $126m  

Hamburg shipowner enters tanker segment with methanol-ready newbuildings delivering from Q4 2026.

Ammonia fuel system component. Wärtsilä boosts ammonia engine power output to match LNG equivalent  

Finnish technology group raises Wärtsilä 25 Ammonia engine output, enabling simpler vessel designs.

Aerial view of a cruiseship at sea. Fincantieri secures order for three LNG-fuelled cruise ships from Princess Cruises  

Italian shipbuilder to construct vessels at Monfalcone yard, with deliveries scheduled through 2039.


↑  Back to Top