LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Caroline Yang, Diana Mok and Francois-Xavier Accard, IBIA. IBIA appoints three new members to Asia regional board  

Caroline Yang, Diana Mok and Francois-Xavier Accard join the board following unanimous approval.

Reimei vessel. MOL achieves 98% methane slip reduction in LNG-fuelled vessel trials  

Japanese shipping company exceeds target in demonstration trials aboard coal carrier operating between Japan and Australia.

Seaside LNG logo. Seaside LNG expands C-suite with four industry veterans  

Houston-based firm appoints new leadership team as LNG bunkering market projected to reach $15bn by 2030.

International Maritime Organization (IMO) headquarters. ICS calls for swift adoption of global regulatory framework  

Secretary general notes MEPC discussions were constructive, but that many member states were still not in a position to adopt the framework without further changes.

WSC quote on maritime discussions. WSC welcomes 'constructive engagement' on global emissions reduction measure  

The liner industry has invested $150bn in dual-fuel ships, but emissions reductions depend on a global framework, notes WSC CEO.

MEPC 84 session. IMO committee agrees intersessional work to rebuild consensus on emissions framework  

Two meetings scheduled before December session as members seek convergence on mid-term greenhouse gas measures.

Map showing existing and planned Emission Control Areas (ECAs). IMO adopts Northeast Atlantic ECA covering waters from Portugal to Greenland  

New ECA to enter into force in September 2027, connecting existing European zones with Canadian Arctic waters.

Renewable and low-carbon methanol project pipeline chart as of April 2026. Renewable methanol project pipeline reaches 61 MMT as China groundbreakings accelerate  

GENA Solutions reports pipeline growth despite concerns over construction readiness for Chinese projects.

Rendering of a diesel-electric chemical tanker. Berg Propulsion to supply propulsion system for Akdeniz-built chemical tanker  

Turkish shipyard Akdeniz orders diesel-electric propulsion package for an 8,000-dwt vessel destined for Transka Tankers.

Ningyuan Diankun vessel. China Classification Society certifies 740-teu pure-electric container ship  

Ning Yuan Dian Kun features battery-swapping capability and is claimed to eliminate 1,462 tonnes of CO2 annually.


↑  Back to Top