This is a legacy page. Please click here to view the latest version.
Mon 24 Sep 2012 08:11

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


MPA and DNV sign MoU. MPA Singapore and DNV renew partnership to advance maritime decarbonisation and digitalisation  

Third MoU renewal focuses on zero-emission fuels, smart-ship systems, and talent development initiatives.

AET and Samsung Heavy Industries logo side by side. AET orders two LNG dual-fuel Suezmax tankers from Samsung Heavy Industries  

Singapore-based tanker operator to expand dual-fuel fleet with vessels featuring advanced efficiency and emissions reduction technologies.

Port of Tallinn and Ports of Stockholm sign MoU. Port of Tallinn and Ports of Stockholm launch green collaboration for fossil fuel-free shipping  

Estonian and Swedish ports sign MoU to promote sustainable maritime transport on Baltic Sea routes.

Grupo Ibaizabal vessel render. NextDF engines achieve 0.9% methane slip for Ibaizabal's LNG bunkering vessel  

Factory tests show methane emissions far below FuelEU Maritime threshold on newbuild.

Steve Esau, Sea-LNG. Sea-LNG welcomes EU transport plan's recognition of methane decarbonisation pathway  

Industry coalition says STIP validates investments in LNG, bio-methane, and e-methane for shipping.

Port of Bell Bay and Bell Bay Industrial Precinct. TasPorts and H2U Group sign MoU to explore green ammonia production at Bell Bay  

Feasibility study to assess 500,000 tonne per year green ammonia facility in northern Tasmania.

Ostend Hydrogen Refuelling Station. JERA Nex bp commissions hydrogen refuelling station at Port of Ostend  

Facility will initially serve Windcat's Hydrocat 48 as part of EU-funded demonstration project.

Methanol bunkering training simulator. Anglo-Eastern launches methanol bunkering simulator with Wärtsilä for seafarer training  

Ship manager introduces simulator and courses to train crew in safe handling of methanol fuel.

ATH Catamba vessel. ATH Trading adds bunker tanker to Angola fleet  

Commodity trader deploys M/T ATH Catamba in Luanda for offshore marine fuel supply operations.

European Union member state flags. Danish Shipping calls for EU to invest ETS revenues in green marine fuel production  

Industry body welcomes Commission's sustainable transport plan but urges concrete action on funding.


↑  Back to Top


 Recommended