This is a legacy page. Please click here to view the latest version.
Mon 24 Sep 2012, 08:11 GMT

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Aurelia NGX 40 launching graphic. Lubmarine launches dual-fuel engine oil for gas operations  

TotalEnergies unit claims product enables extended service life and reduced maintenance costs.

Side view of a cargo vessel. DNV clarifies FuelEU Maritime flexibility mechanisms ahead of first reporting deadline  

Classification society explains banking, borrowing, and pooling options for vessel compliance balances.

Kinetics and Amogy partnership agreement. Kinetics invests in Amogy to deploy ammonia power for floating infrastructure  

London-based Kinetics backs ammonia-to-power firm to develop zero-emission solutions for Powerships and data centres.

Maria Skipper Schwenn, Danish Chamber of Commerce. Maria Skipper Schwenn steps down from IBIA board  

Danish Chamber of Commerce role prompts departure after eight months on association's global board.

Corvus Energy Blue Whale NxtGen battery system. Corvus Energy unveils LFP battery system for marine applications  

Battery supplier targets lower lifecycle costs and 15-year lifespan with Blue Whale NxtGen.

Norwegian Viva vessel. Norwegian Viva receives waste-based biofuel in Piraeus through World Fuel-EKO collaboration  

World Fuel Services coordinates delivery as Norwegian Cruise Line Holdings extends biofuel programme.

Golden Sirius vessel. Golden Island delivers B100 biofuel to Maersk vessels in Singapore  

Golden Island completes two UCOME biofuel deliveries to containerships in October and November.

Beijing Maersk at Tema Port. Beijing Maersk becomes largest vessel to call at Ghana's Tema Port  

Maersk's dual-fuel methanol ship highlights West Africa's transshipment potential and decarbonisation efforts.

Saudi Arabia flag. Saudi Arabia bans open-loop scrubber use with HSFO at its ports  

Ships must switch to compliant fuel or closed-loop systems, GAC advises.

IMO Technical Seminar on Marine Biofuels graphic. IMO to host technical seminar on marine biofuels in February 2026  

International Maritime Organization opens speaker nominations for London event focused on low-GHG fuel adoption.


↑  Back to Top


 Recommended