This is a legacy page. Please click here to view the latest version.
Mon 24 Sep 2012 08:11

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Graphic announcing sectoral action on black carbon. Clean Arctic Alliance calls for Arctic states to submit polar fuels proposal by December 5 deadline  

Environmental group urges IMO member states to act on black carbon emissions following COP30 announcement.

$35M Retrofit Fund Illustration. GCMD closes world's first pay-as-you-save vessel retrofit fund at $35 million  

Fund links repayments to verified fuel savings, offering unsecured leases to overcome financing barriers.

Benny Hilström, WinGD. Where next for LNG fuel after IMO carbon pricing pause?  

WinGD’s Benny Hilström examines what lies ahead for LNG as a marine fuel.

Aasvaer Vessel. Wärtsilä secures sixth hybrid propulsion order from Aasen Shipping for bulk carrier series  

Norwegian shipowner orders integrated system for 9,500 DWT vessel under construction at Royal Bodewes.

COP30 Belém Brazil logo. Danish Shipping to push for IMO climate deal at COP30 after October setback  

Industry body seeks alliances with climate-ambitious nations following postponement of Net-Zero Framework vote.

Petrobras Global Trading seeks bunker trader for Rotterdam operations  

Brazilian energy company's Dutch subsidiary advertises role focusing on marine fuel sales in Brazil.

Tristar Eco Voyager vessel. TotalEnergies charters hybrid lubricants bunkering barge for Fujairah operations  

Tristar-owned vessel combines electric and biofuel power to reduce emissions by up to 35%.

European Commission headquarters. EU awards funding to 70 alternative fuels infrastructure projects across Europe  

€600m funding will support ammonia bunkering, shore power, and charging infrastructure across 24 member states.

Naming ceremony of NOCC Pacific. Norwegian Car Carriers' LNG dual-fuel, ammonia-ready PCTC is named  

NOCC Pacific has received DNV's 'Ammonia-ready' notation, preparing it for the use of lower-carbon fuels.

Graphic announcing the release of the DNV Net-Zero Guidance Paper. DNV and WMMF release guide to help shipowners navigate path to net-zero  

Guide offers practical roadmap for decarbonisation amid evolving regulations and commercial pressures.


↑  Back to Top


 Recommended