This is a legacy page. Please click here to view the latest version.
Mon 24 Sep 2012, 08:11 GMT

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Closing ceremony of vessel with builder’s hull no. 0315874. LNG dual-fuel crude tanker handed over to Capital  

Jiangsu New Times Shipbuilding delivers the 155,500-DWT LNG dual-fuel crude oil vessel Amor.

Lowina Lundstrom, Gasum. Gasum names Lowina Lundström as vice president, biogas  

Former EIT InnoEnergy executive joins Gasum's management team to lead biogas business development from 1 December.

PIL and Huanghai Shipbuilding contract signing. PIL orders seven methanol-ready feeder vessels from Huanghai Shipbuilding  

Singapore carrier's 1,400-TEU newbuilds will boost intra-Asia capacity and support its 2050 net zero target.

MPA and Qingdao Port work plan signing ceremony. Singapore and Qingdao sign work plan to advance green and digital shipping corridors  

MPA and Shandong Port Group’s Qingdao Port have agreed to pursue methanol bunkering pilots and data-sharing initiatives between the two ports.

Delfin Midstream FLNG unit render. Wärtsilä to supply dual-fuel engines and thrusters for Delfin Midstream's FLNG vessel  

Finnish technology group lands propulsion order for first floating LNG vessel built for US Gulf export project.

Uni-Fuels Logo. Uni-Fuels advertises for senior bunker trader in Dubai  

Nasdaq-listed firm recruiting for its trading team as it aims to drive growth.

Mineral Europa vessel. Green ammonia bunkered to ammonia-powered bulk carrier in Australian first  

Pilbara Ports, Fortescue and CMB.Tech complete a ship-to-ship ammonia transfer at Port Hedland, supporting plans for a clean fuel bunkering hub in the region.

Sea Change II vessel render. US Coast Guard agrees design framework for hydrogen-fuelled New York ferry  

Switch Maritime and Incat Crowther reach regulatory agreement for a 150-passenger hydrogen fuel cell-electric fast ferry intended for New York's waterways.

Auto Advance vessel. UECC fits WE Tech hybrid power systems on newbuild ro-ro vessels  

Norwegian short-sea operator says battery and shaft generator technology from WE Tech Solutions has cut fuel use and auxiliary engine reliance on three newbuilds.

Terra Clove vessel. Envision's green ammonia used to bunker world's first VLAC  

Chinese energy group supplies vessel owned by Eastern Pacific Shipping as it links production and marine fuel supply chains.


↑  Back to Top