This is a legacy page. Please click here to view the latest version.
Mon 24 Sep 2012, 08:11 GMT

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Petrobras logo. Petrobras doubles invoiced price of MGO and LSMGO  

Export tax by Brazil's federal government forces Petrobras to double distillate invoice values.

Bunkering of Viking Line's Viking Glory by a Gasum vessel in Turku, Finland. Gasum renews FuelEU Maritime pooling partnerships with Viking Line and Wallenius SOL  

Nordic energy company extends compliance pooling arrangements with two shipping companies operating bio-LNG vessels.

Naming ceremony for CMA CGM Carmen on 18 March 2026. CMA CGM names methanol-powered container ship CMA CGM Carmen  

French shipping line christens 15,000-teu vessel as part of its alternative fuel fleet expansion.

Graphic promoting Singapore Shipping Association marine green fuels training course. Singapore Shipping Association launches marine green fuels training course  

One-day programme covers supply chains, emissions accounting and infrastructure for biofuels, methanol, ammonia and hydrogen.

The Hua Hong 68 at the terminal of Sinochem Xingzhong Oil Staging, Zhoushan. China launches first domestic biofuel blending pilot at Zhoushan port  

Sinochem Xingzhong begins processing 2,000 tonnes of biodiesel with high-sulphur fuel oil.

'AeroLNG' ship with WindWings installation. Bureau Veritas approves BAR Technologies’ WindWings power calculation method for tanker installations  

Classification society validates computational approach for quantifying wind-assisted propulsion under IMO frameworks.

The bunkering tanker Avenir Accolade. Stolt-Nielsen sells 50% stake in Avenir LNG to NYK Line  

The two shipping groups will jointly own the LNG bunkering business.

David Ortiz, trading manager at Sonan Energy Panama. Sonan Energy Panama appoints David Ortiz as trading manager  

Former US Marine brings nearly a decade of bunker trading experience to Panama role.

The M/T Jutlandia Swan, operated by Uni-Tankers. Project CLEANSHIP begins collecting operational data from wingsail-equipped tanker  

M/T Jutlandia Swan serves as floating laboratory to measure wind-assisted propulsion performance.

Bernhard Schulte Shipmanagement's (BSM) second methanol dual-fuel bulk carrier. BSM adds second methanol dual-fuel bulk carrier to managed fleet  

Ship manager now operates two methanol-capable vessels as alternative fuel adoption continues in the bulk sector.


↑  Back to Top


 Recommended