New Crowley video shows arrival of massive LNG tanks at Jaxport bunkering facility


Tanks to be used to refuel Crowley's LNG-powered ConRo ships, El Coqui and Taino.



Crowley Maritime Corp. has released a video to show how two massive cryogenic storage tanks were delivered to its new shoreside liquefied natural gas (LNG) bunkering facility being constructed at the Port of Jacksonville's (Jaxport) Talleyrand Marine Terminal.

The new LNG bunkering facility will fuel Crowley's two new LNG-powered, combination container/roll-on, roll-off (ConRo) ships, which are to be used in the U.S. mainland to Puerto Rico trade.

Eagle LNG Partners' natural gas liquefaction plant in Maxville, Florida, which also is under construction, will supply LNG for the tanks. Once completed, the facility will be able to produce 200,000 gallons of LNG per day (87,000 gallons per day initially). The plant features a one million-gallon storage tank and an LNG truck-loading system.

The newly delivered 260-tonne tanks, which are 170 feet long - exceeding the width of an American football field - were manufactured by Chart Ferox in the Czech Republic. Crowley's logistics group managed the transport of the tanks, first via river barge to Hamburg, Germany, and then via a specialized heavy-lift ship that sailed more than 4,000 nautical miles to arrive in Jacksonville on 26th March for offloading.

"The highly anticipated arrival of these remarkable LNG storage tanks is an important milestone in our project. It further demonstrates we are firmly in the era of LNG fueling," said Sean Lalani, president of Eagle LNG Partners.

With an outer diameter of 19 feet, each tank features an inner shell to hold the product and an outer shell that is insulated and kept under vacuum, to keep the LNG cold. The tanks have a rating of minus 320 degrees Fahrenheit, and each can hold 1,000 cubic metres (approximately 265,000 gallons) of LNG.

The tanks are fitted with two internal LNG pumps, each of which can deliver a flow rate of 900 gallons per minute with the ability to run multiple pumps for a maximum of 2,400 gallons per minutes at peak load rate. Each tank holds sufficient product to fuel Crowley's two LNG-powered vessels within an eight-hour period.

The design of the Talleyrand LNG fuel depot was developed jointly by Eagle and Crowley's LNG engineers in consultation with Jaxport, the U.S. Coast Guard and the Jacksonville Fire and Rescue Department.

The new bunkering terminal utilizes state-of-the art technology to allow safe and efficient transfer operations in a working cargo terminal while minimizing the overall terminal footprint.

Designed specifically for service between Jacksonville and Puerto Rico, the Commitment-class ConRo ships, El Coqui and Taino, will use clean LNG as their primary fuel. El Coqui, which was launched on 20th March, is expected in service in the second half of 2017, and the Taino is slated to begin service in the first half of 2018.

"The new bunkering facility, which we are developing with our partners, Eagle LNG and Jaxport, demonstrates Crowley's commitment to service innovation, particularly as it relates to utilizing a cleaner, more eco-friendly fuel for our new ConRo ships," said Tucker Gilliam, Crowley's vice president of special projects. "The net result of this and other major investments in our Puerto Rico service will be a faster, more efficient and environmentally-friendly supply chain solution for our customers."

The Talleyrand LNG fuel depot is expected to be operational in late summer 2017 prior to arrival of the first Crowley ship.

The Commitment-class project by Crowley features a $550 million investment that includes the next generation ships as well as a new 900-foot pier, three new specialized cranes, and new gate and terminal operating systems at the company's Isla Grande Terminal in San Juan, Puerto Rico.

A link to the video showing the arrival of Crowley's LNG storage tanks has been provided below.

Video: LNG tanks arrive at Crowley's Jacksonville bunkering facility


Flag of Brazil. Petrobras resumes bunkering operations at Rio Grande Terminal after power restoration  

Brazilian supplier restarts marine fuel supply after completing an inspection following an electricity outage.

Stena E-Flexer vessel render. Stena RoRo orders battery-ready E-Flexer 2.0 ferries from Chinese yard  

Vessels include diesel engines capable of running on biodiesel and are methanol-ready.

BW Gemini vessel. Nord Gas Solutions to supply cargo and fuel systems for eight BW LPG VLGCs  

Gas-handling systems specialist awarded contract for new 90,000-cbm vessels.

Kingston Trader vessel. TFG Marine fits mass flow meter to Jamaica-bound bunker barge  

Kingston Trader becomes the first Caribbean bunkering vessel with mass flow metering as TFG Marine’s fleet coverage nears 90%.

Sebastian Vasquez and Camilo Angulo Ferrand, Monjasa. Monjasa announces full-chain marine fuel operations in Cartagena  

Monjasa says it now covers the entire marine fuel supply chain in Colombia, from oil wells to ship-side deliveries.

Steel-cutting ceremony for vessel with builder's hull no. H619. Ceremonies held for Van Oord’s methanol-hybrid rock installation vessels  

Two ships advance through parallel construction at China’s CIMC Raffles shipyard.

WK NatPower and AREL MoU signing. Wah Kwong NatPower signs MoU to explore Hong Kong marine electrification  

Venture will examine shore power, vessel charging and electric vessel deployment around Aberdeen’s waterfront.

Vard 4 39 design render. Dong Fang Offshore orders CSOV with battery-hybrid propulsion  

Vard secures fifth newbuild contract from Taiwanese firm, with delivery scheduled for 2028.

Rock Star vessel. CSL and OWL launch first subsea rock installation vessel for offshore wind  

MV Rock Star can run on MGO and methanol and is designed to support scour protection and cable burial for offshore wind projects.

François Michel and Andy McKeran. Lloyd’s Register study backs 200,000-cbm LNG carriers for fleet renewal  

Analysis finds larger LNG carriers could cut transport costs while retaining access to most major terminals.


↑  Back to Top