Tue 19 Jun 2018, 07:46 GMT

How to prevent bunker spills: North P&I


P&I club lists the main causes of bunker spills and how they can be avoided.


Image credit: North of England P&I Club
North of England P&I Club (North P&I) has issued an overview of the main causes of bunker spills and how they can be avoided.

The marine insurance provider notes that the environmental impact of spilled heavy fuel oil (HFO) can be more severe than a crude oil cargo - whilst lighter fractions of crude can evaporate, residual fuels will not and are therefore described as 'persistent'.

And whilst the release of fuel oil can occur if a tank is breached - due to a collision or impact with a fixed or floating object (FFO) - North P&I notes that many bunker spills take place during bunkering operations and that the "vast majority" of them can be avoided.

Many bunker spills occur when a fuel tank overflows during the bunkering process, North P&I explains. A ship's storage tanks will be designed to overflow into the designated overflow tank and if the overflow tank fills completely, the fuel spills out of the tank vent head, onto the deck and into the water.

Overflow tanks can also fill up when the bunker manifold is over-pressurised and the system's safety valve relieves the pressure into the overflow tank.

North P&I lists the main causes of bunker spills as being:

- Not acting on overflow alarms

Overflow tanks are fitted with float alarms that activate when a set level is reached. These are usually positioned quite low in the tank to allow plenty of time for the engineers to act. On some vessels, a flow switch is fitted to the manifold safety valve drain line, which activates an alarm if flow is detected. In some incidents, overflow alarms have activated but the crew did not take immediate action to investigate.

- Overflow alarms not fitted or not working

There is no statutory requirement to fit alarms to the overflow system and in such cases crew vigilance and suitable monitoring of the overflow tank contents is vital. For those vessels fitted with such alarms, it is important that they are periodically tested to ensure that they will provide the all-important early warning when it really matters.

- Failure to monitor bunker tank levels

The crew must not rely on tank high level alarms and overflow alarms during bunkering. The tank levels must be monitored throughout, paying particular attention when tanks are almost full and changing over to new tanks. If the wrong valve is accidentally operated, a tank level could rise and overflow unless detected and corrected by a vigilant engineer.

- No effective watch at the bunker station

The bunker station should be manned during the bunkering operation. This not only provides visual monitoring and checking for pollution, but is also an important means of communicating with the supplying vessel or barge.

- Communication between bunker barge and receiving vessel

There must be a means of communication between the supplying and receiving vessels' personnel at all times. If a problem occurs that requires an emergency stop of the transfer, the two vessels must be able to communicate immediately. It is good practice to test these communication channels prior to commencing operations.

- Not following procedures or the bunker checklist

A vessel's bunker checklist can be lengthy and there may be a temptation to bypass some of the instructions to speed up the process. This can have costly consequences. Shipowners should ensure that the checklist and supporting policies and procedures are sensible and workable. The vessel's crew must appreciate the importance of the procedures and understand their purpose.

- Supplier exceeding maximum pressure or flow rate

Before bunkering commences, the supplying and receiving vessel must agree a maximum transfer rate and a maximum pumping pressure. There have been instances where the supplier has attempted to exceed these limits to speed up the transfer and has resulted in overflow.

- Defects to bunker piping or tanks

Less common are spills caused by defects to the bunker piping or tanks. Bunker system pipework, fittings and vents that are poorly maintained or neglected can fail in service. Implementing and following a sensible but robust planned maintenance program will prevent the bunker system failing into such a dangerous condition.


Castrol Logo. BP to sell 65% stake in Castrol to Stonepeak for $10bn enterprise value  

Deal brings BP's divestment programme to $11bn, with proceeds earmarked for debt reduction.

Clippership 24-metre class autonomous wind-powered vessel. RINA approves design for Clippership's 24-metre autonomous wind-powered cargo vessel  

Classification society to supervise construction of zero-emission ship featuring twin rigid wings for transatlantic operations.

CMA CGM Antigone vessel. Bureau Veritas classes first methanol dual-fuel boxship as CMA CGM takes delivery  

The 15,000-teu CMA CGM Antigone was built by CSSC Jiangnan Shipyard in China.

AiP award ceremony for floating nuclear plant design. Samsung Heavy Industries' floating nuclear plant design wins ABS approval  

Concept features twin KAERI small modular reactors and a compartmentalised layout to support offshore nuclear power generation.

Claire-Celine Bausager Jørgensen, Dan-Bunkering. Dan-Bunkering Europe appoints Claire-Celine Bausager Jørgensen as senior fuel supplier  

Jørgensen returns to bunker trading after several years in the company's HR department.

CMA CGM Tivoli vessel. DHL and CMA CGM partner on 8,990-tonne biofuel purchase for ocean freight decarbonisation  

Logistics and shipping firms to use UCOME biofuel, targeting 25,000-tonne CO2e reduction.

FincoEnergies Logo. Glencore to acquire majority stake in Dutch marine fuel supplier FincoEnergies  

Transaction expected to complete in Q2 2026, subject to EU anti-trust approval.

CMA CGM Eugenie naming ceremony. CMA CGM names 15,000-teu methanol-fuelled containership CMA CGM Eugenie  

Vessel to operate on Phoenician Express service linking Asia, Middle East, and Mediterranean.

Christian Larsen, Island Oil. Island Oil appoints Christian Larsen as senior trader in Denmark expansion  

Marine fuel supplier establishes operations in Denmark as part of expansion strategy.

HIF Global and Government of Uruguay MoU signing. HIF Global signs Uruguay agreement to advance US$5.3bn e-fuels facility in Paysandú  

Memorandum sets roadmap for final investment decision on plant targeting 880,000 tonnes annual production.