Mon 24 Sep 2012 08:11

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.

Chart showing percentage of off-spec and on-spec samples by fuel type, according to VPS. Is your vessel fully protected from the dangers of poor-quality fuel? | Steve Bee, VPS  

Commercial Director highlights issues linked to purchasing fuel and testing quality against old marine fuel standards.

Ships at the Tecon container terminal at the Port of Suape, Brazil. GDE Marine targets Suape LSMGO by year-end  

Expansion plan revealed following '100% incident-free' first month of VLSFO deliveries.

Hercules Tanker Management and Hyundai Mipo Dockyard sign bunker vessel agreement Peninsula CEO seals deal to build LNG bunker vessel  

Agreement signed through shipping company Hercules Tanker Management.

Illustration of Kotug tugboat and the logos of Auramarine and Sanmar Shipyards. Auramarine supply system chosen for landmark methanol-fuelled tugs  

Vessels to enter into service in mid-2025.

A Maersk vessel, pictured from above. Rise in bunker costs hurts Maersk profit  

Shipper blames reroutings via Cape of Good Hope and fuel price increase.

Claus Bulch Klausen, CEO of Dan-Bunkering. Dan-Bunkering posts profit rise in 2023-24  

EBT climbs to $46.8m, whilst revenue dips from previous year's all-time high.

Chart showing percentage of fuel samples by ISO 8217 version, according to VPS. ISO 8217:2024 'a major step forward' | Steve Bee, VPS  

Revision of international marine fuel standard has addressed a number of the requirements associated with newer fuels, says Group Commercial Director.

Carsten Ladekjær, CEO of Glander International Bunkering. EBT down 45.8% for Glander International Bunkering  

CFO lauds 'resilience' as firm highlights decarbonization achievements over past year.

Anders Grønborg, CEO of KPI OceanConnect. KPI OceanConnect posts 59% drop in pre-tax profit  

Diminished earnings and revenue as sales volume rises by 1m tonnes.

Verde Marine Homepage Delta Energy's ARA team shifts to newly launched Verde Marine  

Physical supplier offering delivery of marine gasoil in the ARA region.


↑  Back to Top


 Related Links