Plant | Company | New Capacity | Start Date |
Anqing | Sinopec | 70,000 | Sep 2012 |
Beihai | Sinopec | 100,000 | Sep 2011 |
Changling | Sinopec | 100,000 | Jun 2011 |
Dagang* | PetroChina/Rosneft | 260,000 | 2013/14 |
Gaoqiao | Sinopec | 34,000 | Q2 2010 |
Guangxi | PetroChina | 200,000 | Sep 2010 |
Huabei | PetroChina | 100,000 | Dec 2012 |
Huizhou | CNOOC | 200,000 | 2013/14 |
Jieyang | PetroChina/PDVSA | 400,000 | 2013/14 |
Jilin | PetroChina | 50,000 | Nov 2010 |
Jinling | Sinopec | 160,000 | end 2011 |
Jiujiang | Sinopec | 60,000 | 2012 |
Kunming* | CNPC | 200,000 | 2013 |
Liaoyang | PetroChina | 50,000 | Oct 2010 |
Luoyang | Sinopec | 40,000 | Oct 2010 |
Maoming* | Sinopec | 240,000 | 2015 |
Ningxia | CNPC | 100,000 | end 2011 |
Qilu | Sinopec | 50,000 | Apr 2010 |
Qingyang | PetroChina | 60,000 | Oct 2010 |
Quanzhou | Sinochem | 240,000 | 2013/14 |
Sichuan | PetroChina | 200,000 | 2012 |
Shijiazhuang | Sinopec | 60,000 | 2012/13 |
Tianjin | Sinopec | 200,000 | Jan 2010 |
Zhanjiang* | Sinopec/KPC | 350,000 | 2013/14 |
Zhenhai* | Sinopec | 180,000 | 2015 |
Plant | Company | New Capacity |
Beihai | Sinopec | 200,000 |
Chongqing | PetroChina | 200,000 |
Fujian | Sinpec/Exxon/Aramco | 240,000 |
Hebei | CNOOC/Zhongjie | 200,000 |
Haihua | CNOOC | 100,000 |
Huizhou | CNOOC | 360,000 |
Jiangsu | PetroChina/Shell/Qatar | 200,000 |
Liaoning | CNPC | 200,000 |
Ningbo | Sinochem | 240,000 |
Shangqiu | PetroChina | 200,000 |
Zhejiang | Sinopec | 300,000 |
![]() |
Swedish biomethane bunkered in Gothenburg
Test delivery performed by St1 and St1 Biokraft, who aim to become large-scale suppliers. |
|
|
||
![]() |
Cockett to be closed down after 45 years
End of an era as shareholders make decision based on 'non-core nature' of Cockett's business. |
|
|
||
![]() |
Petrobras confirms prompt availability of VLS B24 at Rio Grande
Lead time for barge deliveries currently five days. |
|
|
||
![]() |
IMO approves pricing mechanism based on GHG intensity thresholds
Charges to be levied on ships that do not meet yearly GHG fuel intensity reduction targets. |
|
|
||
![]() |
VARO Energy expands renewable portfolio with Preem acquisition
All-cash transaction expected to complete in the latter half of 2025. |
|
|
||
![]() |
NYK trials biofuel in milestone coal carrier test
Vessel is used to test biofuel for domestic utility company. |
|
|
||
![]() |
H-Line Shipping orders LNG bunkering vessel
Vessel with 18,000-cbm capacity to run on both LNG and MDO. |
|
|
||
![]() |
How to engineer and manage green shipping fuels | Stanley George, VPS
Effective management strategies and insights for evolving fuel use. |
|
|
||
![]() |
Swedish government bans scrubber wastewater discharges
Discharges from open-loop scrubbers to be prohibited in Swedish waters from July 2025. |
|
|
||
![]() |
MAN Energy Solutions achieves 100% load milestone for ammonia engine
Latest tests validate fuel injection system throughout the entire load curve. |
|
|