Mon 17 Nov 2008 10:50

Durban refinery to close for 3-4 months


Engen spokesman gives estimated time-frame following last week's fire.



South African refiner and bunker supplier Engen Petroleum Ltd. has said that its bunker-producing refinery in Durban looks set to be closed for up to 120 days following a fire on Thursday morning.

Speaking to news agency Reuters, Engen spokesman Herb Payne said "It could be anything from three to four months."

"I don't know when we will have a better estimate of the time as a lot of it relates to sourcing of equipment from abroad."

The fire, which is reported to have taken place shortly after midnight on Thursday, broke out in the refinery's crude unit, which feeds crude oil into the refinery's processing units. Payne said the cause of the fire was still unknown, but the company believed it could have been a mechanical issue.

Engen has already said that it will implement contingency plans to import refined fuel in order to avoid any shortages.

The Durban refinery, which is 80 percent-owned by Malaysia's state-owned oil company Petroliam Nasional Bhd. (Petronas), is one of the principal supply sources for the South African bunker market.

The port of Durban is the country's largest in terms of cargo volume and marine fuel sold. It accounts for approximately 70 percent of total bunker demand in South Africa, which is estimated to be approximately 3.3 million metric tonnes per year. Annual volumes at the port are around 2.3 million tonnes.

Martin Vorgod, CEO of Global Risk Management. Martin Vorgod elevated to CEO of Global Risk Management  

Vorgod, currently CCO at GRM, will officially step in as CEO on December 1, succeeding Peder Møller.

Dorthe Bendtsen, KPI OceanConnect. Dorthe Bendtsen named interim CEO of KPI OceanConnect  

Officer with background in operations and governance to steer firm through transition as it searches for permanent leadership.

Bunker Holding's executive management team, from left to right: CCO Anders Grønborg,  COO Peder Møller, CEO Keld R. Demant and CFO Michael Krabbe. Bunker Holding revamps commercial department and management team  

CCO departs; commercial activities divided into sales and operations.

Image of a bunker delivery being performed by Peninsula's Hercules 8000 tanker vessel. Peninsula extends UAE coverage into Abu Dhabi and Jebel Ali  

Supplier to provide 'full range of products' after securing bunker licences.

A screenshot taken from Peninsula's homepage on October 4, 2024. Peninsula to receive first of four tankers in Q2 2025  

Methanol-ready vessels form part of bunker supplier's fleet renewal programme.

Stephen Robinson, pictured on his appointment as Head of Bunker Strategy and Procurement at Tankers International. Stephen Robinson heads up bunker desk at Tankers International  

Former Bomin and Cockett MD appointed Head of Bunker Strategy and Procurement.

Chart showing percentage of off-spec and on-spec samples by fuel type, according to VPS. Is your vessel fully protected from the dangers of poor-quality fuel? | Steve Bee, VPS  

Commercial Director highlights issues linked to purchasing fuel and testing quality against old marine fuel standards.

Ships at the Tecon container terminal at the Port of Suape, Brazil. GDE Marine targets Suape LSMGO by year-end  

Expansion plan revealed following '100% incident-free' first month of VLSFO deliveries.

Hercules Tanker Management and Hyundai Mipo Dockyard sign bunker vessel agreement Peninsula CEO seals deal to build LNG bunker vessel  

Agreement signed through shipping company Hercules Tanker Management.

Illustration of Kotug tugboat and the logos of Auramarine and Sanmar Shipyards. Auramarine supply system chosen for landmark methanol-fuelled tugs  

Vessels to enter into service in mid-2025.


↑  Back to Top