Thu 18 Jun 2015 08:32

Project to build Southeast Asia's largest oil terminal 'delayed'


Source tells Reuters that 'there's not enough demand in the region right now'.



China's Sinopec Corp says that it will delay the construction of what would be Southeast Asia's largest oil storage terminal due to slow demand, Reuters reports, citing industry sources.

Plans to build a 2.6 million-cubic-metre storage facility in Indonesia's Batam free trade zone, located south of Singapore, was expected to become operational by mid-2016, but construction has yet to commence and the terminal will not be ready for at least another three to five years, sources told Reuters.

"There's not enough demand in the region right now," a source familiar with the project said, adding that a number of the new storage projects recently built in Malaysia had not yet been filled. "It's about the timing to the market."

The lack of land space for the further expansion of oil facilities in Singapore - Asia's leading oil trading hub - has led to significant investment in the development of storage terminals in nearby Malaysia and Indonesia.

Sinopec subsidiary Sinopec Kantons Holdings holds a 95 percent stake in the Batam terminal. The remaining 5 percent is owned by a local Indonesian firm.

In 2012, Reuters reported that Sinopec and its partner would spend $850 million on the project. The plan was to initially store 1.9 million cubic metres of crude and fuel oil and 730,000 cubic metres of diesel, jet fuel and gasoline. However, the aforementioned delay may lead to Sinopec changing its plans for the project, a source said, adding that the strategy could be redesigned to focus on crude and oil products equally.

Sinopec Kantons is expected to tender for the engineering, procurement and construction (EPC) contract of the Batam terminal within the next few months, a market source informed Reuters.

Martin Vorgod, CEO of Global Risk Management. Martin Vorgod elevated to CEO of Global Risk Management  

Vorgod, currently CCO at GRM, will officially step in as CEO on December 1, succeeding Peder Møller.

Dorthe Bendtsen, KPI OceanConnect. Dorthe Bendtsen named interim CEO of KPI OceanConnect  

Officer with background in operations and governance to steer firm through transition as it searches for permanent leadership.

Bunker Holding's executive management team, from left to right: CCO Anders Grønborg,  COO Peder Møller, CEO Keld R. Demant and CFO Michael Krabbe. Bunker Holding revamps commercial department and management team  

CCO departs; commercial activities divided into sales and operations.

Image of a bunker delivery being performed by Peninsula's Hercules 8000 tanker vessel. Peninsula extends UAE coverage into Abu Dhabi and Jebel Ali  

Supplier to provide 'full range of products' after securing bunker licences.

A screenshot taken from Peninsula's homepage on October 4, 2024. Peninsula to receive first of four tankers in Q2 2025  

Methanol-ready vessels form part of bunker supplier's fleet renewal programme.

Stephen Robinson, pictured on his appointment as Head of Bunker Strategy and Procurement at Tankers International. Stephen Robinson heads up bunker desk at Tankers International  

Former Bomin and Cockett MD appointed Head of Bunker Strategy and Procurement.

Chart showing percentage of off-spec and on-spec samples by fuel type, according to VPS. Is your vessel fully protected from the dangers of poor-quality fuel? | Steve Bee, VPS  

Commercial Director highlights issues linked to purchasing fuel and testing quality against old marine fuel standards.

Ships at the Tecon container terminal at the Port of Suape, Brazil. GDE Marine targets Suape LSMGO by year-end  

Expansion plan revealed following '100% incident-free' first month of VLSFO deliveries.

Hercules Tanker Management and Hyundai Mipo Dockyard sign bunker vessel agreement Peninsula CEO seals deal to build LNG bunker vessel  

Agreement signed through shipping company Hercules Tanker Management.

Illustration of Kotug tugboat and the logos of Auramarine and Sanmar Shipyards. Auramarine supply system chosen for landmark methanol-fuelled tugs  

Vessels to enter into service in mid-2025.


↑  Back to Top