Thu 30 May 2013 18:05

Zeebrugge: LNG jetty understructure completed


Jetty for loading and unloading LNG carriers is scheduled to enter into service in 2015.



The Port of Zeebrugge's project to develop an LNG bunkering infrastructure is moving forward following the completion of the understructure for the second LNG jetty, which was undertaken by Wilrijk-based contractor MBG.

With the understructure completed, Fluxys Belgium - an operator of natural gas transmission grid and storage infrastructure in the country - can begin to build the superstructure.

For this stage of the project, Spanish-Italian firm TS LNG has been appointed as contractor. The company is a joint venture between TechInt E&C and SENER.

The second jetty for loading and unloading LNG carriers is scheduled to enter into service in 2015. The jetty will be able to accommodate both small and large LNG carriers, with capacities of between 2,000 and 217,000 cubic metres of LNG.

The Port of Zeebrugge says it has already seen a rise in LNG export volumes. When the second jetty enters into service in 2015, this will enable to the port to increase its flexibility in being able to handle LNG imports and exports.

"With the construction of the second jetty, Port of Zeebrugge continues to evolve into a hub for the supply of LNG as a fuel for ships and long-distance haulage trucks," the port said.

Image: Port of Zeebrugge.

Martin Vorgod, CEO of Global Risk Management. Martin Vorgod elevated to CEO of Global Risk Management  

Vorgod, currently CCO at GRM, will officially step in as CEO on December 1, succeeding Peder Møller.

Dorthe Bendtsen, KPI OceanConnect. Dorthe Bendtsen named interim CEO of KPI OceanConnect  

Officer with background in operations and governance to steer firm through transition as it searches for permanent leadership.

Bunker Holding's executive management team, from left to right: CCO Anders Grønborg,  COO Peder Møller, CEO Keld R. Demant and CFO Michael Krabbe. Bunker Holding revamps commercial department and management team  

CCO departs; commercial activities divided into sales and operations.

Image of a bunker delivery being performed by Peninsula's Hercules 8000 tanker vessel. Peninsula extends UAE coverage into Abu Dhabi and Jebel Ali  

Supplier to provide 'full range of products' after securing bunker licences.

A screenshot taken from Peninsula's homepage on October 4, 2024. Peninsula to receive first of four tankers in Q2 2025  

Methanol-ready vessels form part of bunker supplier's fleet renewal programme.

Stephen Robinson, pictured on his appointment as Head of Bunker Strategy and Procurement at Tankers International. Stephen Robinson heads up bunker desk at Tankers International  

Former Bomin and Cockett MD appointed Head of Bunker Strategy and Procurement.

Chart showing percentage of off-spec and on-spec samples by fuel type, according to VPS. Is your vessel fully protected from the dangers of poor-quality fuel? | Steve Bee, VPS  

Commercial Director highlights issues linked to purchasing fuel and testing quality against old marine fuel standards.

Ships at the Tecon container terminal at the Port of Suape, Brazil. GDE Marine targets Suape LSMGO by year-end  

Expansion plan revealed following '100% incident-free' first month of VLSFO deliveries.

Hercules Tanker Management and Hyundai Mipo Dockyard sign bunker vessel agreement Peninsula CEO seals deal to build LNG bunker vessel  

Agreement signed through shipping company Hercules Tanker Management.

Illustration of Kotug tugboat and the logos of Auramarine and Sanmar Shipyards. Auramarine supply system chosen for landmark methanol-fuelled tugs  

Vessels to enter into service in mid-2025.


↑  Back to Top