This is a legacy page. Please click here to view the latest version.
Mon 25 Sep 2017, 07:11 GMT

Wartsila outlines 'new opportunities for supplying LNG' with FSRB concept


Floating storage and regasificaton barge is designed to enable the supply of LNG in areas where it was previously not possible.



Wartsila says its floating storage and regasificaton barge (FSRB) concept offers "new opportunities for supplying LNG" to locations where it was previously not possible.

The company's flexible barge-mounted storage and regasification solution has storage capacities ranging from 7,500 to 30,000 cubic metres. It has been developed to serve a new market by bringing smaller volumes of LNG to areas that are not possible to reach with floating storage and regasification units (FSRUs), or where the building of an onshore facility is not economically viable. For example:

- Where an onshore tank facility is difficult to build.

- Where the regulatory permits to build onshore are difficult to obtain.

- Where the water is too shallow for FSRUs and large-scale LNG carriers.

- Where a temporary solution is needed while more permanent facilities are being developed.

- Where limited demand cannot support a large fixed facility or a conventional large-scale FSRU.

- Where the demand is temporary, and a solution that can later be relocated or sold elsewhere is preferred.

- Where flexibility for adapting to changing market conditions is essential. Capacity can quickly be increased by adding an additional barge.

The Wartsila FSRB can be utilised to supply gas for power production or other consumers, to provide LNG bunkering for ships, or for distribution via tanker trucks.

It is being marketed by Wartsila as an economically viable, fast delivery solution for providing LNG storage and regasification facilities to areas where the conventional infrastructure is limited, or entirely absent.

Wartsila cites some of the key advantages of using the FSRB as being:

- It is a floating facility that can be moved from one location to another.

- It saves time in obtaining regulatory approvals needed by land-based terminals.

- It requires relatively low capital investment, especially for remote locations and islands where local materials and labour may be limited or unavailable.

- Since the FSRB is unmanned, operating costs are low.

- Delivery time is short, typically one year.

- Financing can be easier to obtain since it is a flexible re-sellable asset.

Mooring

Because each location has its own characteristics, Wartsila has developed different mooring concepts to suit the particular situation. The following five concepts represent typical solutions:

1. FSRB mooring at shore concept

This covers situations where no existing jetty or quay is available. Wartsila constructs an appropriate mooring facility to provide a physical connection to dry land.

2. FSRB mooring at a quay concept

In this case, there is an existing quay where both the barge and the visiting LNG carrier can be moored. It is not, therefore, necessary to construct an expensive mooring structure where simple modifications are sufficient.

3. FSRB mooring at a jetty concept

If it is necessary to construct a jetty, its length depends on the local bathymetric water depths. The jetty must be at a depth where small-scale LNG carriers can safely berth and offload their cargo. The FSRB is permanently moored at the jetty and the LNG carrier can dock either next to the barge for ship-to-barge transfer, or can deliver the LNG via cross-jetty transfer.

4. FSRB as a landlocked concept

Where the local geotechnical conditions are poor, excavations can be carried out to create a small pond or lagoon with an access canal to the open water. When the barge has been floated into the lagoon, the canal is filled in and the barge is 'landlocked'. It can be moored by ropes to bollards on the land. This is a solution particularly suited to swamps and very low, wet land. A connection will be necessary to transfer LNG from the supplying carrier to the barge. This can be made either by a jetty or by using a floating LNG hose that can be connected to the carrier.

5. Jettyless LNG transfer concept

This solution is applicable when the visiting LNG carrier is conventionally spread moored near shore. The hoses are floated from an on-shore hose reel and the barge is towed out to the LNG carrier for unloading. The barge's own unloading arm is then attached to the carrier with mooring ropes. This solution enables small-scale LNG transfers to the LNG storage on shore or to the landlocked FSRBs.

Handling boil-off gas

Storage of the LNG is in a number of independent Type-C tanks. When liquefied gas is stored for longer periods, heat flux from the surroundings will increase the temperature inside the tank, thus causing the liquid to evaporate. The generated gas from this is known as boil-off gas (BOG). The BOG has a larger volume than the LNG from which it was created, which in turn increases the pressure inside the tank. The Type-C tanks can handle internal pressures up to 6 bar, which allows them to store the BOG for longer periods, whereas membrane or land-based atmospheric tanks require the BOG to be handled much sooner.

Where the FSRB is supplying gas to a nearby electricity generating power plant, the BOG can be fed easily via a low-pressure pipeline to the plant. This represents a cost-efficient means of handling the BOG. Similarly, waste heat generated by the power plant can be fed back to the barge to be utilised in the regasification process.

Regasification

The regasification systems used on the FSRB utilise either the water/glycol system, taking heat from a nearby source such as a power plant, or ambient air vaporisers. Ambient air vaporisers use the heat in the surrounding air to vaporise the LNG into gaseous form.

Flexibility

The barge is equipped with similar processes as those on land-based satellite and bunkering facilities. The processes can also be split between the barge and land. This can be achieved, for example, by locating the LNG storage tanks on the barge and the process equipment and support facilities onshore.

Also, The modular design of both the barge hull and the onboard storage tanks makes scaling up or down easy, and there is always the option of adding a second barge if one alone cannot provide sufficient storage capacity.

Additionally, the barge is unmanned during normal operations and because it is unpropelled, there are no special demands or restrictions by the marine authorities.


Kuehne+Nagel logo. Kuehne+Nagel seeks marine energy pricing analyst in Greece  

Logistics firm recruiting for role focused on bunker pricing formulas and compliance cost analysis.

Fulvio Astengo, LD Ports & Logistics. LD Armateurs to present floating ammonia terminal concept at London energy conference  

French shipowner to showcase FRESH platform design for offshore hydrogen and ammonia supply chains.

NACKS bulk carriers with rotor sails. Anemoi rotor sails complete eight years of operation on bulk carrier M/V Afros  

Lloyd’s Register survey finds no operational issues with wind propulsion system after extended service.

Mikkel Kannegaard, Bunker Holding. Bunker Holding promotes Mikkel Kannegaard to chief operating officer  

Kannegaard has led transformation of supply organisation since joining in August 2025.

London skyline. Uni-Fuels seeks general manager for London bunker trading desk  

Nasdaq-listed marine fuel supplier recruits for commercial leadership role with P&L responsibility.

VPS logo. NE Atlantic ECA will cause significant change to the current fuel mix | Steve Bee, VPS  

The possibility of off-spec issues highlights the continuing need for proactive fuel testing to protect vessels.

Kris Vedat, SmartSea. Smart ships failing to convert data into actionable intelligence, warns SmartSea  

Maritime technology firm claims vessels collect vast amounts of data but lack integration to support decision-making.

Energy Transition Outlook 2026 Hydrogen To 2060 report cover. DNV forecasts 100-fold growth in clean hydrogen by 2060, with China leading expansion  

Classification society projects $3.2tn investment in hydrogen sector, with maritime accounting for 15% of clean hydrogen use.

World Shipping Council logo. Dual-fuel container ship and vehicle carrier fleet surpasses 1,200 vessels  

World Shipping Council reports 65% year-on-year increase in operational dual-fuel vessels to 440 ships.

Sotiris Raptis, ECSA. European Shipowners calls for ETS revenue investment and fuel supplier mandate  

ECSA urges the EU to invest €9bn in annual ETS revenues in fuel production and infrastructure.


↑  Back to Top