This is a legacy page. Please click here to view the latest version.
Mon 25 Sep 2017, 07:11 GMT

Wartsila outlines 'new opportunities for supplying LNG' with FSRB concept


Floating storage and regasificaton barge is designed to enable the supply of LNG in areas where it was previously not possible.



Wartsila says its floating storage and regasificaton barge (FSRB) concept offers "new opportunities for supplying LNG" to locations where it was previously not possible.

The company's flexible barge-mounted storage and regasification solution has storage capacities ranging from 7,500 to 30,000 cubic metres. It has been developed to serve a new market by bringing smaller volumes of LNG to areas that are not possible to reach with floating storage and regasification units (FSRUs), or where the building of an onshore facility is not economically viable. For example:

- Where an onshore tank facility is difficult to build.

- Where the regulatory permits to build onshore are difficult to obtain.

- Where the water is too shallow for FSRUs and large-scale LNG carriers.

- Where a temporary solution is needed while more permanent facilities are being developed.

- Where limited demand cannot support a large fixed facility or a conventional large-scale FSRU.

- Where the demand is temporary, and a solution that can later be relocated or sold elsewhere is preferred.

- Where flexibility for adapting to changing market conditions is essential. Capacity can quickly be increased by adding an additional barge.

The Wartsila FSRB can be utilised to supply gas for power production or other consumers, to provide LNG bunkering for ships, or for distribution via tanker trucks.

It is being marketed by Wartsila as an economically viable, fast delivery solution for providing LNG storage and regasification facilities to areas where the conventional infrastructure is limited, or entirely absent.

Wartsila cites some of the key advantages of using the FSRB as being:

- It is a floating facility that can be moved from one location to another.

- It saves time in obtaining regulatory approvals needed by land-based terminals.

- It requires relatively low capital investment, especially for remote locations and islands where local materials and labour may be limited or unavailable.

- Since the FSRB is unmanned, operating costs are low.

- Delivery time is short, typically one year.

- Financing can be easier to obtain since it is a flexible re-sellable asset.

Mooring

Because each location has its own characteristics, Wartsila has developed different mooring concepts to suit the particular situation. The following five concepts represent typical solutions:

1. FSRB mooring at shore concept

This covers situations where no existing jetty or quay is available. Wartsila constructs an appropriate mooring facility to provide a physical connection to dry land.

2. FSRB mooring at a quay concept

In this case, there is an existing quay where both the barge and the visiting LNG carrier can be moored. It is not, therefore, necessary to construct an expensive mooring structure where simple modifications are sufficient.

3. FSRB mooring at a jetty concept

If it is necessary to construct a jetty, its length depends on the local bathymetric water depths. The jetty must be at a depth where small-scale LNG carriers can safely berth and offload their cargo. The FSRB is permanently moored at the jetty and the LNG carrier can dock either next to the barge for ship-to-barge transfer, or can deliver the LNG via cross-jetty transfer.

4. FSRB as a landlocked concept

Where the local geotechnical conditions are poor, excavations can be carried out to create a small pond or lagoon with an access canal to the open water. When the barge has been floated into the lagoon, the canal is filled in and the barge is 'landlocked'. It can be moored by ropes to bollards on the land. This is a solution particularly suited to swamps and very low, wet land. A connection will be necessary to transfer LNG from the supplying carrier to the barge. This can be made either by a jetty or by using a floating LNG hose that can be connected to the carrier.

5. Jettyless LNG transfer concept

This solution is applicable when the visiting LNG carrier is conventionally spread moored near shore. The hoses are floated from an on-shore hose reel and the barge is towed out to the LNG carrier for unloading. The barge's own unloading arm is then attached to the carrier with mooring ropes. This solution enables small-scale LNG transfers to the LNG storage on shore or to the landlocked FSRBs.

Handling boil-off gas

Storage of the LNG is in a number of independent Type-C tanks. When liquefied gas is stored for longer periods, heat flux from the surroundings will increase the temperature inside the tank, thus causing the liquid to evaporate. The generated gas from this is known as boil-off gas (BOG). The BOG has a larger volume than the LNG from which it was created, which in turn increases the pressure inside the tank. The Type-C tanks can handle internal pressures up to 6 bar, which allows them to store the BOG for longer periods, whereas membrane or land-based atmospheric tanks require the BOG to be handled much sooner.

Where the FSRB is supplying gas to a nearby electricity generating power plant, the BOG can be fed easily via a low-pressure pipeline to the plant. This represents a cost-efficient means of handling the BOG. Similarly, waste heat generated by the power plant can be fed back to the barge to be utilised in the regasification process.

Regasification

The regasification systems used on the FSRB utilise either the water/glycol system, taking heat from a nearby source such as a power plant, or ambient air vaporisers. Ambient air vaporisers use the heat in the surrounding air to vaporise the LNG into gaseous form.

Flexibility

The barge is equipped with similar processes as those on land-based satellite and bunkering facilities. The processes can also be split between the barge and land. This can be achieved, for example, by locating the LNG storage tanks on the barge and the process equipment and support facilities onshore.

Also, The modular design of both the barge hull and the onboard storage tanks makes scaling up or down easy, and there is always the option of adding a second barge if one alone cannot provide sufficient storage capacity.

Additionally, the barge is unmanned during normal operations and because it is unpropelled, there are no special demands or restrictions by the marine authorities.


210,000-tonne tri-fuel ore vessel render. CSSC units sign contract for four tri-fuel ore carriers  

Ships feature a tri-fuel propulsion system combining ethanol, methanol and fuel oil.

Houston skyline. Bunker One seeks oil derivatives trader for Houston desk  

New hire to work alongside trading and sales, providing hedging solutions for physical exposure.

Lyla Pathfinder vessel. Kawasaki delivers 13th LPG-fuelled LPG/ammonia carrier  

86,700-cbm vessel is shipbuilder's 20th delivery featuring LPG-fuel propulsion.

Mein Schiff Relax ship-to-ship (STS) bunkering operation. TUI Cruises puts both InTUItion-class ships on bio-LNG as fleet targets 50,000-tonne CO₂e saving in 2026  

German cruise operator says bio-LNG use across two newbuilds has already cut 26,000 tonnes of CO₂e.

MCE Marine Surveyors logo. MCE Marine Surveyors seeks bunker surveyor in Rotterdam amid growing demand  

Liquid bulk surveyor certificate listed as a preference, as is prior experience in a bunker surveyor role.

Athinagoras vessel. LNG dual-fuel tanker delivered to Capital Ship Management  

Vessel one of two handed over to Greek operators on the same day.

Auramarine quality specialist hiring announcement. Auramarine seeks quality specialist to unify European and Asian management systems  

Finnish fuel supply system maker is recruiting a quality specialist to harmonise its global operations.

Nave Orbit vessel. Navios Maritime Partners takes delivery of LNG- and methanol-ready Aframax tanker  

117,012-dwt Nave Orbit features alternative-fuel readiness and energy-efficiency technology.

PetroChina Petroineos Trading logo. PetroChina International seeks bunker sales manager to drive European growth  

Chinese state-owned energy trader targets ARA expansion with new commercial hire.

CF Anja vessel. Damen delivers HVO-ready CF 3850 to Lithuania’s Juru Agentura Forsa  

CF Anja marks the first newbuild vessel in Forsa’s dry cargo fleet.


↑  Back to Top