This is a legacy page. Please click here to view the latest version.
Thu 22 Jun 2017, 09:45 GMT

Gard highlights mass flow meter 'discrepancies'


P&I club issues recommendations to ensure bunker barge operator compliance.



Source: Gard

Protection and indemnity (P&I) insurer Gard aims to address in this article the issues faced by members when taking bunkers in Singapore following the mandatory implementation of mass flow meters (MFM) for bunker suppliers. The introduction of mandatory use of MFMs was intended to address frequent quantity disputes arising between the bunker barge and the receiving vessel, although issues remain.

Causes of the discrepancies

There have been two main causes of the discrepancies when using the mass flow meter;

- Operational practices by the bunker barge operators, and

- Limitations of the equipment itself.

Operational practices

Gard has received reports indicating that some bunker barges were found to syphon fuel back to their tanks via pipe connections between the flow meter and the outlet flange going to the ship manifold. In such circumstances the MFM reading will be higher than the amount actually received by the ship's bunker tanks.

The Maritime Port Authority of Singapore is currently investigating these issues and has suspended several barges from operations until completion of the investigation. It is worth noting that an MPA-certified bunker barge should have all connections between the flow meter and the shipside blanked off and sealed as part of the certification.

Limitations of the MFMs

Some vessels have recently reported quantity difference exceeding their past experience. Some bunker surveyors have studies the discrepancy between the MFM readings and the vessel received figures for a duration of time. Out of 24 cases of discrepancies over the duration, the maximum discrepancy was 57.24 MT and minimum 6.79 MT. The average discrepancy, in the disputed cases, was approximately 19 MT.

These discrepancies can be due to:

- Errors in the tank calibration tables for the receiving vessel.

- Errors in the MFM's measurement of the flow rate.

Any errors in the tank calibration of the vessel would be consistent with or without the MFM. To identify this issue a vessel experience factor (VEF) from her previous bunkering operations should be taken into account.

Errors in the MFM reading can also account for such discrepancies. All MFMs have a maximum and minimum flow rate, commonly known as 'Qmax' and 'Qmin' respectively. These limits define the operational accuracy within which the system is qualified to operate. In other words, if the flow rate of the liquid is outside these limits, the calibration of the equipment may not be accurate. It is seldom that the flow rate exceeds the Qmax, as it is usually about 1,000 t/h (forward flow). However, during stripping of the bunker barge's tanks, the flow rate can frequently fall below the Qmin. The longer the duration of the stripping, the more likelihood of a discrepancy between the MFM and the ship's received figures.

Additionally, MFM parameters such as Damping, Drive Gain, Low Flow Cut Off Value & Air Index can affect the accuracy of measurement if they exceed the manufacturers' recommended limits during the bunkering operation.

While stripping of the bunker tanks is allowed under the TR48 (Technical Reference For Bunker Mass Flow Metering), it has been noted that prolonged stripping operations causes frequent fluctuations in the flow rate with several instances of the flow rate falling below the Qmin. It has also been observed that some bunker barges conduct stripping operations in the middle of bunkering which is not permitted under TR48 and can lead to measurement uncertainty.

Recommendations

To ensure that bunker barge operators comply with all the necessary requirements, Gard recommends the following;

1. Compare the certificate of the MFM with the actual equipment fitted on the barge (comparing the serial number) to verify that the certificate is for the equipment actually fitted.

2. Seal checks: there are a number of seals, up to 20 in some cases, fitted on the MFM and other piping on the barge. These seals have to be checked and verified before every delivery.

3. The bunker surveyors should inspect the barge piping, especially around the manifold areas for any drain lines, fittings or stub pieces from where bunker oil may be tapped back into the barge tanks. If any such fittings are found, the surveyors are instructed to seal any valves leading to such fittings and report the vessel's chief engineer to the Maritime Port Authority of Singapore. The surveyor should also ensure that the Meter Totalizer Log is available for inspection as required under TR48.

4. Meter Zero should be the last thing that is done before commencing the bunker delivery and must always be done AFTER the hose has been fitted to the ship's manifold.

5. Where the bunker surveyor has been engaged, the survey report should indicate an evaluation of the meter profile in order to ensure that the basic MFM profile parameters (Qmin, Damping, Drive Gain, Low Flow Cut Off Value & Air Index) are within operating limits.

6. If there is significant discrepancy between the vessel received figures and the MFM figures after having physically verified all the above points, the following actions are recommended:

7. Repeat steps 2 and 3 as stated above.

8. Inform the MPA following the guidelines on 'Mass Flow Meter Dispute Management'

9. Engage an MFM advisor to study the meter profile in detail. This will involve the MFM profile ASCII files, Transmitter Configuration Report etc. The surveyor should also be asked to provide an independent opinion on the validity of the delivered quantity.

In addition to the physical checks, members and clients could consider incorporating protective clauses in their bunker purchase contracts. The protective clauses could include the provision of the need to physically check the bunker quantities on the delivery barge before and after bunkering.


American Bureau of Shipping (ABS) logo. ABS introduces nuclear-ready notation for marine and offshore assets  

The classification society has released what it describes as an industry-first notation to support future nuclear conversion of vessels and offshore assets.

AiP handover ceremony for NEXTGEN Energy Hub (NGEH) design. ABS grants approval in principle for Seatrium’s NEXTGEN Energy Hub design  

The hub concept integrates ammonia bunkering, power generation and electric vessel charging in a single unit.

Jumbo Maritime crew aboard vessel. Jumbo orders two methanol-ready L-Class heavy lift vessels from Dajin Heavy Industry  

Dutch heavy lift specialist Jumbo signs newbuilding contract for two 25,000-dwt vessels.

China flag. Zhoushan completes first bonded bunker operation at Majishan port area  

The operation marks full fuel supply coverage across all general cargo terminals in Zhoushan's port system.

US dollar banknotes. Port of Long Beach launches $1m methanol bunkering challenge for oceangoing vessels  

A $1m prize aims to kick-start commercial methanol bunkering at one of North America's busiest ports.

Core Power, Athlos Energy, Deon Policy Institute and ABS logos. Greece floating nuclear study finds no fundamental barriers to implementation  

A PESTLE assessment of floating nuclear power plants in Greece identifies framework gaps, not feasibility barriers.

Northern Pathliner alongside Bergen LNG vessel. Molgas completes LNG cool-down and bunkering for Northern Pathliner at Northern Lights terminal in Norway  

Operation carried out at Øygarden facility, with K Line and Integr8 Fuels in the supply chain.

Rendering of a G2 Ocean OHGC vessel. G2 Ocean expands fleet with six future-fuel ready gantry crane vessels  

Open hatch specialist adds vessels and jet sail technology as part of a broad fleet renewal programme.

CMA CGM Adventure vessel at Port of Mombasa. LNG-powered CMA CGM Adventure makes first call at the Port of Mombasa  

Kenya Ports Authority receives its first large LNG-fuelled container vessel.

Liam Blackmore, Lloyd's Register. Maritime trio shapes IMO safety guidelines for ammonia as marine fuel  

Real-world operational experience feeds directly into new IMO ammonia fuel safety framework.


↑  Back to Top